Miscellaneous action | | | 9/12/2005 | | DONE |
|
|
|
Sent email notice to Tom Easton addressing lack of information incorporating FlexHead connectors.
|
INSP-Final Inspection | 9/8/2005 | 9/8/2005 | 9/9/2005 | P | FAIL |
Forrest France
|
|
|
One head as shown on approved plans is not installed in the reception area, review notes and submitted plans do not include the flex heads as used throughout the space.
|
INSP-Final Inspection | 9/8/2005 | 9/9/2005 | 9/9/2005 | A | PASS |
Forrest France
|
|
|
Fire sprinkler passed inspection, verification is pending for approval of the flex heads as used throughout the space and not submitted for on the plans.
|
Plan resubmittals received | | | 9/8/2005 | | DONE |
|
|
|
|
Issue permit | | | 9/8/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 9/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/7/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (Bill) | 8/19/2005 | | 9/6/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/19/2005 | | 9/6/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2005 | | DONE |
|
|
|
|
Application received | | | 8/19/2005 | | |
|
|
|
|