| INSP-Final Inspection | 3/10/2006 | 3/13/2006 | 3/13/2006 | A | PASS |
Forrest France
|
|
|
Shell alarm permit is complete, TI alarm finaled.
|
| INSP-Final Inspection | 2/27/2006 | 2/28/2006 | 2/28/2006 | P | PART |
Forrest France
|
|
|
c/n items are complete, final pending shell alarm permit final.
|
| Alarm Plan Check | | | 2/28/2006 | | PASS |
|
|
|
Plan Modification, received plans with the appropriate locations of all AHU duct detectors. Approved pending field inspection of fire alarm permit comments.
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2006 | | DONE |
|
|
|
|
| CHANGE STATUS TO (ISS) | | | 2/28/2006 | | DONE |
|
|
|
per mary change status to issued
|
| Plan resubmittals received | | | 2/15/2006 | | |
|
|
|
|
| INSP-Final Inspection | 2/3/2006 | 2/6/2006 | 2/6/2006 | A | DEFR |
Forrest France
|
|
|
Require approved resubmitted plans for the AHU addresses and changed av location for verification prior to final.
|
| Alarm Plan Check | | | 11/17/2005 | | FAIL |
|
|
|
Resubmittal required for the AHU duct detector locations. Will accept the revised plan only.
Phoned Charlie Bayne (Simplex-applicant) to inform him. No written comments at this time.
|
| Plan resubmittals received | | | 11/4/2005 | | |
|
|
|
|
| INSP-Final Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | P | NR |
Forrest France
|
|
|
Pending shell life safety, sprinkler and alarm permit approvals prior to TI finals.
|
| INSP-Final Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | P | PART |
Forrest France
|
|
|
Temp occupancy approval per D.Hanneman pending resubmittals reflecting changes.
|
| INSP-Alarm Testing | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | PART |
Forrest France
|
|
|
Devices tested satisfactory, final pending resubmittals for relocated av and address changes on duct detectors.
|
| INSP-Sprinkler Rough-in | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | FAIL |
Forrest France
|
|
|
AHU #1 and #2 do not match approved plan with respect to location and addressing, AV at back wall adjacent to registers is obstructed by clothing racks, AHU #3 detector needs to be relocated as discussed, provide resubmittals reflecting the required changes.
|
| INSP-Alarm Testing | 10/24/2005 | 10/24/2005 | 10/24/2005 | P | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 10/24/2005 at 8:01:03 AM. Contact: ###-####. cancel
|
| (F) Reprint permit | | | 10/11/2005 | | DONE |
|
|
|
|
| CHANGE STATUS TO (ISS) | | | 10/11/2005 | | DONE |
|
|
|
already issued previously
|
| Alarm Plan Check | | | 10/10/2005 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 10/10/2005 | | DONE |
|
|
|
|
| Inspection Record Card- Fire | 10/10/2005 | | 10/10/2005 | | DONE |
|
|
|
|
| Telephone call | | | 10/10/2005 | | DONE |
|
|
|
Left voice message for Charlie that permit is ready & fees///10/10/05 4:00pm BAS
|
| Plan resubmittals received | | | 10/3/2005 | | |
|
|
|
|
| Case Summary | | | 10/3/2005 | | DONE |
|
|
|
|
| Alarm Plan Check | | | 9/30/2005 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Charlie Bayne.
|
| Plan resubmittals received | | | 9/23/2005 | | DONE |
|
|
|
added build materials per Mary///9/23/05 BAS
|
| Plan resubmittals received | | | 9/22/2005 | | DONE |
|
|
|
|
| Telephone call | | | 9/12/2005 | | DONE |
|
|
|
Phoned Ralph Costelli (architect) to inform him that the FAS for Ann Taylor Loft was designed as a voice/evac system. It now appears that there were circumstances involved with the theatre that required a separation, which in turn created two separate fire areas. Hence only the theatre required voice/evac. The remainder of the first floor of the building is considered an M over 500 and a required manual FAS is required (horn/strobes only).
|
| Inspection Record Card- Fire | 8/31/2005 | | 8/31/2005 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 8/31/2005 | | DONE |
|
|
|
|
| Telephone call | | | 8/31/2005 | | DONE |
|
|
|
tlk to peter ###-#### that permit and fees are ready to be picked up
|
| Issue and Print Permit | | | 8/31/2005 | | DONE |
|
|
|
|
| Plan assigned to (Mary) | 8/19/2005 | | 8/30/2005 | | DONE |
|
|
|
|
| Alarm Plan Check | | | 8/30/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2005 | | DONE |
|
|
|
|
| Case Summary | | | 8/25/2005 | | DONE |
|
|
|
|
| Alarm Plan Check | | | 8/24/2005 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Ronnie Zahm.
|
| Application received | | | 8/19/2005 | | |
|
|
|
|
| Case Summary | | | 8/19/2005 | | DONE |
|
|
|
|