INSP-Final Inspection | 2/15/2006 | 2/17/2006 | 2/17/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 2/14/2006 | 2/15/2006 | 2/15/2006 | P | FAIL |
Troy Cobbley
|
|
|
Need to forward flush the backflow preventor and install one additional hanger at the front entrance.
|
INSP-Final Inspection | 2/1/2006 | 2/2/2006 | 2/2/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need to provide review comments. Need to finish work work at the entrance. It appears one sprinkler needs to be added outside of the entry way. Provide spare heads and head wrench. Provide rest of ceiling tile in the framing room. Provide additional hydraulic stickers for new remote areas at the riser. Verify that the existing backflow does or does not need to be forward flushed to verify the new/higher flow rate of the storage area.
|
INSP-Final Inspection | 11/14/2005 | 11/15/2005 | 11/15/2005 | A | PART |
Troy Cobbley
|
|
|
Could not give final with no ceiling. Piping in and around the new framing room is ok to cover
|
Permit Ready to Issue | | | 10/18/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/18/2005 | | 10/18/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/18/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Issue permit | | | 10/18/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/13/2005 | | 10/17/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2005 | | DONE |
Bill Alexander
|
|
|
|
INSP-Final Inspection | 10/14/2005 | 10/14/2005 | 10/14/2005 | P | FAIL |
Forrest France
|
|
|
Approved resubmitted plans are not available for inspection or verification of compliance.
|
INSP-Final Inspection | 10/13/2005 | 10/13/2005 | 10/13/2005 | P | PART |
Troy Cobbley
|
|
|
Deficiencies for the 6" tie in have been corrected.
|
INSP-Sprinkler Rough-in | 10/12/2005 | 10/13/2005 | 10/13/2005 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for the 6" main. Need to fire caulk around the penatration to the fire riser room, provide additional clearance at thepenatrationthrough the CMU wall and provide a 4 way brace at the top of the 6" rise up piece in the future stock room.
|
Plan resubmittals received | | | 10/13/2005 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2005 | 10/10/2005 | 10/10/2005 | P | FAIL |
Troy Cobbley
|
|
|
Can not do a final as the sprinkler plans need to be resubmitted. Sprinkler piping is ok to cover in the new area.
|
INSP-Final Inspection | 10/10/2005 | 10/10/2005 | 10/10/2005 | P | FAIL |
Troy Cobbley
|
|
|
Can not do a final as the sprinkler plans need to be resubmitted. Sprinkler piping is ok to cover in the new area.
|
Permit Ready to Issue | | | 10/7/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/7/2005 | | 10/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/7/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Issue and Print Permit | | | 10/7/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/1/2005 | | 10/6/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/6/2005 | | PART |
Bill Alexander
|
|
|
Re-Submittals Of The Following Items Are Required:
1. Area #2 Hydraulic calculations (storage) design is flawed. Minimum sprinkler operating head pressure, for the Tyco Model "ELO-231" S.R., S.C., SSU, 11.2 K-factor TY5111 is 12.76 psi. All sprinklers are incorporating an 11.4 K-factor head which mean this design verification is flawed. Revise and resubmit a correct design for verification.
2. No provisions shown for forward flow testing of the backflow device. If none is provided, riser modifications will be required meeting annual requirements of NFPA 13-16.2.5.1. Address and resubmit clarification.
3. Design installation has problems. Fire sprinklers are cold soldering off the east wall of the new framing shop. The Tyco Model "ELO-231" S.R., S.C., SSU, 11.2 K-factor TY5111 pendants have a minimum fire sprinkler spacing for 9'-0". Sprinklers shall be permitted to be placed less than 8'-0" on center where the conditions of 8.8.3.4.2 are satisfied: Provide corrections and resubmit.
4. Plan FP2 of 2, seismic bracing was not provided for the new 6" main. Provide and resubmit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/30/2005 | | 10/3/2005 | | FAIL |
Troy Cobbley
|
|
|
Plans still have problems with calcs, hangers, Seismic, etc.
|
Sprinkler Plan Check | 9/1/2005 | | 9/29/2005 | | PART |
Troy Cobbley
|
|
|
Re-Submittals Of The Following Items Are Required:
1. The scope of work provided on the permit application does not match what is actually going on.
2. The use of the EC-11 pendant sprinkler heads for Quick Response in ordinary hazard occupancy is not UL listed. See the provided data sheet and call Tyco technical support which is listed on the front of the data sheet as well.
3. The ELO-231 heads are shown to have a SIN number of TY3131 and be Quick Response on the head legend. But per the provided cut sheet is no TY3131 and the heads are not quick response.
4. The hydraulic calculations for Remote Area #1 are not accurate.
No dimensions or node points are given on the site plan.
Pipe size and type is not given on the site plan.
Calcs. show 4" MJ 90 but pipe entering and leaving fitting is 6".
Length of underground on calcs does not match what is scaled.
Fitting counts and point to point lengths as shown on plans don't match calcs.
Node points 40 and 42 are not shown on the plans.
The elevation changes of piping does not match center to center lengths given.
No other items reviewed except as listed above. Review all items for accuracy and resubmit. Upon resubmittal, additional items may be found upon further review.
Approval has been given to proceed with installation of the sprinkler system with the conditions set forth in the signed pre-installation letter.
|
Telephone call | | | 9/26/2005 | | DONE |
|
|
|
tlk to trent bice ###-#### that permit failed and needs to be picked up
|
Plan resubmittals received | | | 9/22/2005 | | DONE |
|
|
|
|
Application received | | | 9/1/2005 | | |
|
|
|
|
Plan assigned to (Bill) | 10/13/2005 | | | | |
Bill Alexander
|
|
|
|