Permit Information
Permit NumberFIR05-00565
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 10259 W EMERALD ST
Project NameSPR EMERALD BLDG D
Customer Number 
ePlanReview 
Description
(PUMP IT UP)(EMERALD BLDG "D") To add and relocate fire sprinkler protection for the remodel of a 9,680-ft/2 portion of an existing 25,339-ft/2 building, to be used as an assembly occupancy. Fire sprinkler work is related to the construction of interior partitions for various game areas and party rooms, new restroom facilities and a new suspended ceiling system with new lighting. This building is fully fire sprinklered. The fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD05-00496.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/20/20104/20/20104/20/2010PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection4/16/20104/19/20104/20/2010PPASS
DetailsTroy Cobbley
permit finaled
Miscellaneous action  3/12/2010 DONE
Sent email requesting project status.
(F) Reprint permit  10/25/2005 DONE
Inspection Record Card- Fire10/24/2005 10/24/2005 DONE
Telephone call  10/24/2005 DONE
called ###-#### and told Trent that permit is ready for pick-up and no fees
Sprinkler Plan Check10/6/2005 10/21/2005 PASS
DetailsBill Alexander
Miscellaneous action  10/21/2005 DONE
Plan Mod taken to permit desk for issueing.
Plan assigned to (Bill)9/2/2005 10/21/2005 DONE
INSP-Final Inspection10/17/200510/18/200510/18/2005APART
DetailsTroy Cobbley
Overspacing has been corrected. Sprinkler piping is ok to cover.
INSP-Final Inspection10/17/200510/17/200510/17/2005PFAIL
DetailsTroy Cobbley
The sprinkler heads that have been modified need hangers taken to the top of the structure and pendant heads are overspaced in two locations. See approved plans.
INSP-Final Inspection10/14/200510/14/200510/14/2005PFAIL
DetailsForrest France
Several items need correction including spacing issues, some missing hangers, missing heads in two locations, see stamped plans for annotations.
Plan resubmittals received  10/6/2005  
DetailsBill Alexander
Permit Ready to Issue  9/21/2005 DONE
Inspection Record Card- Fire9/21/2005 9/21/2005 DONE
Telephone call  9/21/2005 DONE
Spoke with Trent and told him that permit is ready & fees///9/21/05 11:47am BAS
Issue permit  9/21/2005 DONE
Sprinkler Plan Check9/2/2005 9/20/2005 PASS
DetailsBill Alexander
Plans approved with comments
PLANS/APPL TAKEN TO FRONT DESK  9/20/2005 DONE
Application received  9/2/2005