Permit Information
Permit NumberFIR05-00570
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1487 S DAVID LN
Project NameSPR INS NETWORK AMERICA
Customer Number 
ePlanReview 
Description
INSURANCE NETWORK AMERICA OFFICE BUILDING - To install a complete overhead and combustible cavity fire protection system in a new 7,800-ft/2, one story wood framed office building. The underground fire service supply lead-in was installed under FIR05-00460. All fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-01669.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/3/20063/3/20063/3/2006PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection2/16/20062/16/20062/16/2006PPART
DetailsForrest France
The following items remain for final, need to provide for requirements of note #24 on plan review comments regarding one hour riser room construction or PIV installation, perform the forward flow test for the backflow prevention device, provide and attatch hydraulic calc. sticker to the riser.
INSP-Sprinkler Rough-in/Hydro2/9/20062/10/20062/10/2006APART
DetailsForrest France
Hydrostatic test of the overhead fire sprinkler passed.
INSP-Sprinkler Rough-in12/2/200512/5/200512/5/2005APART
DetailsForrest France
Verified the unsprinklered cavity at the west dormer has been completely filled with noncombustible insulation per the exception of NFPA 13 8.14.1.2.7. Overhead rough-in is good for cover.
INSP-Sprinkler Rough-in/Hydro11/18/200511/18/200511/18/2005PPART
DetailsForrest France
Overhead fire sprinkler rough-in is okay to cover pending verification of coverage for the dormer at the west roof that is not currrently protected, also will need to verify no obstructions develop after the insulation is installed at the roof.
Plan assigned to (Bill)9/2/2005 11/9/2005 DONE
Sprinkler Plan Check10/17/2005 11/9/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  11/9/2005 DONE
Permit Ready to Issue  11/9/2005 DONE
Inspection Record Card- Fire11/9/2005 11/9/2005 DONE
Telephone call  11/9/2005 DONE
Called Brad & told him permit ready & fees on 11-9-05 @ 2:18 by BAS
Issue and Print Permit  11/9/2005 DONE
Plan resubmittals received  10/17/2005 DONE
Telephone call  10/13/2005 DONE
called and left messge w/Crystal for Jeff Anderson that permit failed and can pick up
Telephone call  10/13/2005 DONE
customer for treasure valley fire protection picked up plans
Sprinkler Plan Check9/21/2005 10/12/2005 FAIL
DetailsBill Alexander
1. "Reception Area" system calculations:
a. Test area/density head pressure is not for 225-ft/2 spacing as designed, but for a 7 psi minimum head pressure.
b. Calc Nodes 17 to 40 has a butterfly valve for fittings used.
Revise and resubmit a design that meets NFPA 13-14.4.

2. Plan provided have nodes, pipe lengths and dimensioning blended with lines throughout this plan, making it very difficult, if not impossible to interpret for verification of IFC fire protection installation code. Revise and submit plans that are clear and legible.

3. "N.T.S." for the only section view is unacceptable. Provide section view with a correct and identifiable scale.

4. All pendant sprinkler in this facility are using "401" Escutcheons? Provide clarification if there are some obstructions. Plans show "boxes," yet section provides nothing to clarify what they are? Provide plans that include information relating to fire sprinkler design requirements.

5. Correct sprinkler head legend, Reliable F3QR SIN number.

6. Reduction area used in calculations Area #2 is identified as "System #1, Area 1 (on plan FP-2).

7. Calc Area #3, does not meet the minimum remote area of operation required to be verified per 11.2.3.1.5 and does not qualify for the "Room Design Method" in 11.2.3.3. Plan lacks enough detail to determine appropriate separation requirements (addressed in Table 11.2.3.1.1 = 60 minutes) and would not be allowed with an "accordion slider," therefore area of operation must be extended to the area required in 11.2.3.1.5 (15oo-ft/2 with allowable allowance for ceiling reduction incorporating Q.R. sprinkler per 11.2.3.2.3.1). Please revise and resubmit.

8. Address seismic requirements per NFPA 13-14.1.3(39). Include locations and type.

9. Data submittal provided for backflow is identifying a 4" and metric flow?
Sprinkler Plan Check9/26/2005 10/12/2005 FAIL
DetailsBill Alexander
1. "RECEPTION AREA", Test area/density head pressure is not for 225-ft/2 spacing as designed, but for a 7 psi minimum operating head pressure. .10/14.62 = 146-ft/2 maximum area per head verifying and designers head spacing exceed this.
2. "RECEPTION AREA" design is flawed. Ceiling slope exceeds 2 in 12, so area of operation must be increased by 30 percent without revising the density when quick-response sprinklers are used.
Miscellaneous action  10/12/2005 DONE
Taken the failed review documents to the permit desk for returning adn required desing corrections
Miscellaneous action  10/5/2005 DONE
Requested Early Start. 1st review failed, 9/21/2005. 2nd resubmittal received 9/23/2005, failed 10/12/2005. Early Start was approved per attached requirements.
Plan resubmittals received  9/23/2005 DONE
Miscellaneous action  9/21/2005 DONE
I have taken the failed review documents to the permit desk for returning
Telephone call  9/21/2005 DONE
Left message for Jeff that plans failed and need picked up///9/21/05 12:05pm BAS
Case Summary  9/2/2005 DONE
Application received  9/2/2005