Permit Information
Permit NumberFIR05-00575
StatusFinaled
Name FUTURETECH
Site Address 2440 -2494 N BOGUS BASIN RD
Project Namealm - HIGHLANDS VILLAGE BLD 9
Customer Number 
ePlanReview 
Description
To provide a required manual fire alarm system. The required manual fire alarm system includes sprinkler monitoring, elevator recall/shutdown (ISIS elevator) and notification throughout the public spaces. (Per IFC review, manual pull stations are not required if the building alarm system notifies on water flow).

The building permit BLD04-00944 is to construct a new 13,266 sq.ft. three story, four unit apartment building. The first floor is 4,346 sq.ft. which 2,912 sq.ft. is for the garages, the second floor is 4,440 sq.ft. and the third floor is 4,440 sq.ft. Each unit on the second and third floors are single story units, three bedrooms with three bathrooms one full and two 3/4. Note: This building is fire sprinklered per NFPA 13-R for story increase. All construction per the approved plans and attached comment list. THIS LOT IS WITHIN THE FLOODPLAIN AREA. A Elevation Certificate is required before calling for a rough framing inspection. MJP DRH 02-240 CUP 02-0141 2440 & 2442 N Bogus Basin Rd & 2492 & 2494 N Bogus Basin Rd(HIGHLANDS FLOOR PLAN TYPE)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/23/20063/23/20063/23/2006PPASS
DetailsForrest France
Fire alarm passed final inspection.
INSP-Alarm Testing3/20/20063/21/20063/21/2006APASS
DetailsForrest France
Fire alarm passed inspection.
INSP-Alarm Testing3/16/20063/17/20063/17/2006APART
DetailsForrest France
Per state elevator requirements, the top of shaft will require a heat detector, need to test elevator lobby SD 3rd floor north and smoke and heat in top of shaft, outside bell repaired while on site, panel, sprinkler, notification, alarm, supervision, trouble and EOL tested okay, provide signal verification as discussed, provide as-builts and updated map at next inspection, provide signage at the door to the FACP.
INSP-Alarm Testing3/16/20063/16/20063/16/2006ANR
DetailsForrest France
State elevator inspection failed, alarm inspection to be rescheduled.
CHANGE STATUS TO (ISS)  2/16/2006 DONE
for new structure
Plan assigned to (Mary)9/2/2005 2/14/2006 DONE
Alarm Plan Check  2/14/2006 PASS
Approved pending field inspection of fire alarm permit comments.
PLANS/APPL TAKEN TO FRONT DESK  2/14/2006 DONE
Inspection Record Card- Fire2/14/2006 2/14/2006 DONE
Permit Ready to Issue  2/14/2006  
Telephone call  2/14/2006 DONE
tlk to matt casey ###-#### that permit is ready to be picked up no fee
Plan resubmittals received  1/26/2006 DONE
Alarm Plan Check  9/14/2005 FAIL
No comments written. Incorrect monitoring on the Isis elevator.
Application received  9/2/2005