INSP-Final Inspection | 4/28/2006 | 4/28/2006 | 4/28/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection, permit finaled.
|
INSP-Final Inspection | 4/24/2006 | 4/24/2006 | 4/24/2006 | P | PART |
Forrest France
|
|
|
Need to remove "construction caps" at the pendent heads in the showers on the 1st floor, install missing escutcheons at some locations.
|
INSP-Final Inspection | 4/17/2006 | 4/18/2006 | 4/18/2006 | P | FAIL |
Forrest France
|
|
|
Stairway sprinklers must be installed per NFPA 13 2002 8.14.3.2.1.
|
INSP-Final Inspection | 4/14/2006 | 4/17/2006 | 4/17/2006 | A | DEFR |
Forrest France
|
|
|
Inspection rescheduled
|
Inspection Record Card- Fire | 4/12/2006 | | 4/12/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/12/2006 | | 4/12/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/12/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/12/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/10/2006 | | |
|
|
|
|
Plan assigned to (SAM) | 4/10/2006 | | 4/10/2006 | | PASS |
|
|
|
Plan mod - quick review. Faxed plan revisions to add 3 sprinklers in elevator shafts (1 each shaft), one additional sprinkler in enlarged elevator equipment room, and 1 head in new vestibule room at stairwell entrance on penthouse level. No calc's; piping layout hydraulically similar to issued approved plans. Revised stamped plans taken to permit desk to be issued with resubmittal fee.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2006 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 4/6/2006 | 4/6/2006 | 4/6/2006 | P | PART |
Forrest France
|
|
|
The 11th floor overhead rough-in is good for cover at the drop ceiling areas.
|
INSP-Sprinkler Rough-in | 4/4/2006 | 4/4/2006 | 4/4/2006 | P | PART |
Forrest France
|
|
|
Performed standpipe flow test as required.
|
INSP-Sprinkler Rough-in | 3/30/2006 | 3/31/2006 | 3/31/2006 | A | PASS |
Troy Cobbley
|
|
|
sprinkler piping in the lower ceilings on the first floor are ok to cover. See city approved plans for locations . The west side lower ceiling has a lower soffit that will require an additional sprinkler head to provide proper coverage. Also marked on plans.
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2006 | 3/29/2006 | 3/29/2006 | P | PART |
Forrest France
|
|
|
Hydrostatic test of the overhead wet, antifreeze, and standpipe systems is satisfactory, noted one head at the mezzanine stair landing is painted, head cage is missing at head under mezz ductwork, inspected the 5th and 6th floors for cover, the mech penthouse, 11th floor, and portions of the 1st floor are not inspected for cover at this time, discussed items left for completion at the riser room and final testing including standpipe flow test, forward flow of BFP and related sprinkler alarms.
|
INSP-Sprinkler Rough-in | 3/24/2006 | 3/28/2006 | 3/28/2006 | A | PART |
Forrest France
|
|
|
Pump start-up testing performed with manufacturer rep. including churn, rated and 150 percent capacity, manual and automatic starts and stops, jockey pump, set pressures, event log, min. run time, sensing lines, piping arrangements. Performance testing only, no alarm, trouble or supervised conditions tested at this time.
|
INSP-Sprinkler Rough-in | 3/22/2006 | 3/27/2006 | 3/27/2006 | P | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover on floors 10, 9, 8, and 7. Partial inspection of floor 5 as ceiling grid is not complete. Floor 6 and 11 not ready for cover inspection at this time. Also concluded satisfactory 72 hr hydro test of the UG tanks as water level did not drop.
|
INSP-Sprinkler Rough-in | 3/23/2006 | 3/24/2006 | 3/24/2006 | P | PART |
Forrest France
|
|
|
Begin 72hr test of the water level at the underground storage tanks.
|
INSP-Sprinkler Rough-in | 3/16/2006 | 3/17/2006 | 3/17/2006 | P | PART |
Forrest France
|
|
|
Third and fourth floor overhead rough-in is acceptable for cover.
|
INSP-Sprinkler Rough-in | 3/14/2006 | 3/15/2006 | 3/15/2006 | A | PART |
Forrest France
|
|
|
Core areas including the restrooms,elevator lobby, and janitors closet on the 7th-11th floors inspected for rough-in cover, 2nd and 1st floors rough-in is good for cover, one head in the ATM room is blocked by ductwork, discussed hydro testing schedule.
|
INSP-Supply line flush | 3/13/2006 | 3/14/2006 | 3/14/2006 | A | DEFR |
Forrest France
|
|
|
This inspection request was intended for an UG supply line flush under project related permit FIR05-00395-contractor called in the wrong permit number (for overhead), flush was witnessed and performed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2006 | 3/1/2006 | 3/1/2006 | A | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover at the 2nd thru 6th floor core areas including restrooms, elevator lobby, janitors closets, tele rooms and electrical rooms, discussed inspection method for the common floor areas, also inspected corridors and adjacent meeting rooms at the 2nd floor.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2006 | 2/28/2006 | 2/28/2006 | P | CANC |
Forrest France
|
|
|
Inspection to be rescheduled due to time constraints.
|
Sprinkler Plan Check | 2/8/2006 | | 2/24/2006 | | PASS |
Bill Alexander
|
|
|
|
Override - Parcel Holds | | | 2/24/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 2/24/2006 | | 2/24/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 2/24/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 2/24/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/24/2006 | | DONE |
|
|
|
lft vm with gerald ###-#### that permit and fees are ready to be picked up
|
Issue and Print Permit | | | 2/24/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 1/13/2006 | | 2/24/2006 | | DONE |
Bill Alexander
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/24/2006 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 2/13/2006 | 2/14/2006 | 2/14/2006 | A | DONE |
Forrest France
|
|
|
On site confrence to discuss location of the penthouse mechanical room standpipe hose connections.
|
INSP-Sprinkler Rough-in | 2/13/2006 | 2/13/2006 | 2/13/2006 | P | CANC |
Forrest France
|
|
|
Inspection was intended for the UG rough-in under a different permit.
|
INSP-Supply line flush | 2/10/2006 | 2/10/2006 | 2/13/2006 | P | NR |
Forrest France
|
|
|
Per contractor, not ready for inspection, to be rescheduled for next week.
|
INSP-Sprinkler Rough-in | 2/9/2006 | 2/9/2006 | 2/10/2006 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the lining of the tank. Provide access to the interior of the tank for inspection
|
Plan resubmittals received | | | 2/8/2006 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/8/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/13/2006 | | 2/7/2006 | | PART |
Bill Alexander
|
|
|
Plan correction/resubmittal required
ITEM #32. Plan FP-6. An enclosed "canopy" (addressed as such by the designer on Plan FP-6) with one east face opening, located on the 2nd floor, is referenced with no protection incorporating 8.14.7.2, a "Canopy" sprinkler exemption: "Sprinklers shall be permitted to be omitted where the canopy or roof is of noncombustible or limited combustible construction." Per the Building Code, IBC 202 Canopy definition is: "An architectural projection that provides weather protection, identity or decoration and is supported by the building to which it is attached and at the outer end by not less than on stanchion. A canopy is comprised of a rigid structure over which a covering is attached." The area in questions does not apply for this exemption. This facility requires full fire sprinkler protection of which this area is part of part of and will require fire sprinkler protection. Revise and resubmit fire sprinkler protection plans meeting full sprinkler protection.
February 7, 2006 - Designer provided a personal letter from "Gary Christensen" (The Christensen Corporation), of which the response does not address an allowable code exemption for the same. Provide fire sprinkler protection and resubmit for approval.
|
Plan assigned to (Bill) | 2/6/2006 | | 2/7/2006 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/7/2006 | | 2/7/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/7/2006 | | DONE |
|
|
|
called ###-#### and told Gerald that permit ready for pickup and is charged another $105
|
Permit Ready to Issue | | | 2/7/2006 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 2/3/2006 | 2/6/2006 | 2/6/2006 | A | PART |
Forrest France
|
|
|
First floor entry lobby hard lid area inspection only, acceptable to cover at this location only. The 1 1/4 branch line to feed the elevator pit sprinklers has not been installed.
|
Plan resubmittals received | | | 2/3/2006 | | DONE |
|
|
|
|
Case Summary | | | 2/3/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/2/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 1/17/2006 | | 2/1/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/1/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/1/2006 | | DONE |
|
|
|
left mess that is permit is ready
|
Plan resubmittals received | | | 1/13/2006 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 1/12/2006 | 1/12/2006 | 1/12/2006 | P | PART |
Forrest France
|
|
|
Inspected four restrooms on the first floor for overhead rough-in cover.
|
INSP-Sprinkler Rough-in | 1/4/2006 | 1/4/2006 | 1/4/2006 | P | PART |
Forrest France
|
|
|
Inspection for rough-in at 2nd floor hard lid area, sprinklers at ceiling pocket areas must comply with the requirements of note #137 on plan review documents. The updated approved resubmitted plans are required for future overhead inspection requests.
|
Sprinkler Plan Check | | | 12/28/2005 | | FAIL |
|
|
|
Plans had been held pending resubmited information. The information never arrived. I spoke to Gerald and he stated that they are going to resubmit the entire package due to changes. He stated that he didn't want the old copies returned. I faxed my review comments to him.
|
Sprinkler Plan Check | 11/22/2005 | | 11/22/2005 | | FAIL |
|
|
|
Plans review comments faxed to Gerald at Treasure Valley Fire Protection. This is the third review.
|
Plan resubmittals received | | | 10/31/2005 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/12/2005 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/12/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/29/2005 | | 10/11/2005 | | PART |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
Plan assigned to (Bill) | 9/29/2005 | | 10/11/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/11/2005 | | 10/11/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/11/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/11/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Issue permit | | | 10/3/2005 | | |
|
|
|
|
Plan assigned to (Bill) | 9/9/2005 | | 9/29/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/9/2005 | | 9/29/2005 | | PASS |
Bill Alexander
|
|
|
Plans approved with comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/29/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/29/2005 | | 9/29/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/29/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Miscellaneous action | | | 9/27/2005 | | DONE |
|
|
|
Approval granted to written request from G. Ebleling, TVFP to start work prior to issuance of this permit due to current time delay in approvals; faxed approval back to TVFP.
|
Plan resubmittals received | | | 9/23/2005 | | |
|
|
|
|
Application received | | | 9/9/2005 | | |
|
|
|
|