INSP-Final Inspection | 9/16/2008 | 9/16/2008 | 9/16/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 3/31/2006 | 3/31/2006 | 3/31/2006 | P | PASS |
Troy Cobbley
|
|
|
underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2006 | 3/30/2006 | 3/31/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
Plan resubmittals received | | | 3/17/2006 | | |
|
|
|
UG Pipe size modification.
|
INSP-Sprinkler Rough-in | 1/25/2006 | 1/26/2006 | 1/26/2006 | A | PASS |
Troy Cobbley
|
|
|
Three lengths of 6" underground supply piping have been installed along the face of the building. They are ok for cover.
|
INSP-Supply line flush | 10/19/2005 | 10/19/2005 | 10/19/2005 | P | PASS |
Troy Cobbley
|
|
|
Inspection was for stub out cover not flush. Underground stub out passed but has changed from coming out the north side to coming out the northwest side
|
Sprinkler Plan Check | 9/19/2005 | | 9/19/2005 | | FAIL |
|
|
|
Plan on hold to discuss location of sprinkler riser in stairwell enclosure with Bill Alexander and Building plan reviewer. Called TVFP and advised J. Anderson.
|
Sprinkler Plan Check | 9/19/2005 | | 9/19/2005 | | PASS |
|
|
|
The inside riser cannot be located within the 2-hour rated stair enclosure. Per the architect for the TIN permit BLD05-01063, they will be submitting plans within the next couple of days, showing the riser to be separated from the stairwell with a 1-hour rated enclosure having an exterior door. This approval for the underground stub up location is contingent upon receipt and approval of those plans. The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002, AWWA, the IFC-2003. No written review comments; final approval subject to plan annotations and satisfactory inspection by PDS/Fire.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/19/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/19/2005 | | 9/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2005 | | DONE |
|
|
|
Spoke with Jeff and told him that permit is ready & fees///9/19/05 2:20pm BAS
|
Issue permit | | | 9/19/2005 | | |
|
|
|
|
Application received | | | 9/12/2005 | | |
|
|
|
|
Plan assigned to (Bill) | 9/12/2005 | | | | |
|
|
|
|
Sprinkler Plan Check | 3/14/2006 | | | | |
Bill Alexander
|
|
|
|