Description
(AIRPORT MAINTENANCE BUILDING, BOISE AIRPORT - O.A.R.) To install a complete overhead (OH-2) fire sprinkler system with associated underground fire service supply main into and existing 17,100, Type V-B building for (office (B), parking garage-storage (B-1) under the 1979 UBC). Building occupancy permit does not allow underground fire service work will start at the property line service tap on the north side of Enterprise, with 6" C-900 PVC, running south approximately 175'-0", then 90ยบ west under the footing approximately 12'-0" from the inside north wall and 1'-6" from the inside east wall, then up through the floor with 6" C-50 Ductile Iron. (Note: There is no outside control or an outside access in a 1 hour fire separated room shown/provided). The overhead system is a wet grid with a simple "electric" riser. This facility is not allowed to have high piled storage or storage, use of hazardous materials beyond allowable limits and no vehicle repairs. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is not attached to a building permit, but fire protection requirements were addressed under MIS04-00138 to determine requirements for issuance of a certificate of occupancy.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary  1/4/2012  
INSP-Final Inspection12/5/200512/5/200512/5/2005PPASS
DetailsForrest France
Fire sprinkler passed inspection, permit finaled.
INSP-Final Inspection12/2/200512/2/200512/2/2005PNR
DetailsForrest France
The related fire alarm permit must be requested for inspection to enable a final for this sprinkler permit.
INSP-Supply line flush11/14/200511/14/200511/14/2005PPART
DetailsForrest France
UG fire supply line flush performed satisfactory.
INSP-Sprinkler Rough-in/Hydro11/8/200511/9/200511/9/2005APART
DetailsForrest France
Overhead rough-in is satisfactory, AG and UG hydrostatic tests also passed inspection, will final when alarms are connected and forward flow is performed.
Case Summary  11/7/2005  
INSP-Sprinkler Rough-in10/27/200510/27/200510/27/2005PPART
DetailsForrest France
Underground fire supply line is acceptable to cover.
Inspection Record Card- Fire10/18/2005 10/18/2005 DONE
Permit Ready to Issue  10/18/2005  
Telephone call  10/18/2005 DONE
left mess that permit is ready
Issue and Print Permit  10/18/2005 DONE
Plan assigned to (Bill)9/30/2005 10/17/2005 DONE
Sprinkler Plan Check9/30/2005 10/17/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  10/17/2005 DONE
DetailsBill Alexander
Application received  9/30/2005