INSP-Final Inspection | 5/30/2006 | 5/31/2006 | 6/1/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 5/10/2006 | 5/12/2006 | 5/12/2006 | A | FAIL |
Troy Cobbley
|
|
|
carl; Phone #: ###-#### None of the sensors released the doors when an occupant approached or when the fire alarm system was activated.
|
INSP-Final Inspection | 5/10/2006 | 5/10/2006 | 5/10/2006 | P | FAIL |
Troy Cobbley
|
|
|
Contractor not ready for inspection due to cordination issues with locking the doors down for testing
|
INSP-Conference | 4/17/2006 | 4/18/2006 | 4/18/2006 | A | CANC |
Troy Cobbley
|
|
|
Carl; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong /// Cancel per Carl (SCP Global Technologies) 4-18-06 eus
|
INSP-Final Inspection | 3/29/2006 | 4/4/2006 | 4/4/2006 | A | FAIL |
Troy Cobbley
|
|
|
Doors do not meet all 6 requirements of the IFC's Access Controled Egress Doors (sensors do not release upon door activation and some doors are missing sensors). No testing performed.
|
Telephone call | | | 1/26/2006 | | DONE |
|
|
|
customer picked up paperwork
|
INSP-Final Inspection | 1/11/2006 | 1/11/2006 | 1/11/2006 | P | FAIL |
Troy Cobbley
|
|
|
carl harrison; Phone #: ###-#### No approved plans on site. No inspection performed.
|
FIR-Aging Inspection | 1/5/2006 | 1/5/2006 | 1/6/2006 | | NR |
Troy Cobbley
|
|
|
Will be called in next week for inspection
|
Application received | | | 10/5/2005 | | |
|
|
|
|
Plan assigned to (Mary) | 10/5/2005 | | 10/5/2005 | | DONE |
|
|
|
|
Case Summary | | | 10/5/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 10/5/2005 | | PASS |
|
|
|
Approved pending PDS Fire Inspector field verification. No comments written.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2005 | | DONE |
|
|
|
|
Miscellaneous action | | | 10/5/2005 | | DONE |
|
|
|
Rita sent bill with applicant
|
Issue and Print Permit | | | 10/5/2005 | | DONE |
|
|
|
|