INSP-Final Inspection | 4/26/2006 | 4/27/2006 | 4/27/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 4/11/2006 | 4/12/2006 | 4/12/2006 | A | PART |
Forrest France
|
|
|
The remainder of sprinkler relocation work under this permit scope is good for cover as marked on approved plans, final pending ceiling tile and escutcheons.
|
INSP-Sprinkler Rough-in/Hydro | 4/11/2006 | 4/11/2006 | 4/11/2006 | P | DEFR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 4/11/2006 at 8:37:28 AM. Contact: ###-####.
|
INSP-Sprinkler Rough-in/Hydro | 1/16/2006 | 1/17/2006 | 1/17/2006 | A | PART |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 1/16/2006 at 2:23:15 PM. Contact: ###-####.
|
Sprinkler Plan Check | 12/7/2005 | | 12/7/2005 | | PASS |
Bill Alexander
|
|
|
Added scope of work
|
Miscellaneous action | | | 12/7/2005 | | DONE |
|
|
|
Took added scope of work to front desk for calling and releasing.
|
Telephone call | | | 12/7/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Telephone call | | | 12/7/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Telephone call | | | 12/7/2005 | | DONE |
|
|
|
gave permit to brodie
|
Plan resubmittals received | | | 12/5/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/25/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/24/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/24/2005 | | 10/24/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/24/2005 | | DONE |
|
|
|
called ###-#### and told Brodie permit is ready and fees
|
Plan assigned to (Bill) | 10/5/2005 | | 10/21/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/5/2005 | | 10/21/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2005 | | DONE |
|
|
|
|
Case Summary | | | 10/5/2005 | | DONE |
|
|
|
|
Application received | | | 10/5/2005 | | |
|
|
|
|