Permit NumberFIR05-00676
StatusFinaled
Name NORTHWEST SALES COMPANY
Site Address 7960 W NORTHVIEW ST
Project Namealm - ST MARKS
Customer Number 
ePlanReview 
Description
To extend a required manual fire alarm system into the St Marks Food Bank Addition. The existing required manual fire alarm system includes HVAC shutdown, fire/smoke damper control and voice/evac throughout. The food bank is separated from the main building by a 1-hour wall. No entrance into the main building, therefore only horn/strobe notification will be required.

The building permit BLD04-02876 is to construct a 1856 sq. ft. one story, type VB, fully fire sprinklered addition to the north side of existing building A. Other work includes all site improvements and landscaping per approved plans and attachments, CUP02-00038. Fire sprinklers used for area. St Marks Food Bank Addition.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/23/20065/23/20065/23/2006PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection5/23/20065/23/20065/23/2006PPASS
DetailsTroy Cobbley
permit finaled
INSP-Alarm Testing2/13/20062/13/20062/13/2006PPASS
DetailsTroy Cobbley
Fire alarm finaled
Issue and Print Permit  1/31/2006 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/19/2006 DONE
Inspection Record Card- Fire1/19/2006 1/19/2006 DONE
Permit Ready to Issue  1/19/2006 DONE
Telephone call  1/19/2006 DONE
lft vm with rick groom ###-#### that permit and fees are ready to be picked up
INSP-Final Inspection1/17/20061/17/20061/17/2006PPART
DetailsTroy Cobbley
A temporary occupancy was given with Dave Hannemans permission until the revised fire alarm plans are approved. Pull stations and a/v's as installed work.
Alarm Plan Check  1/17/2006 PASS
Plan Modification. Approved pending field inspection of fire alarm permit comments.
Case Summary  1/12/2006 DONE
Plan resubmittals received  1/10/2006 DONE
INSP-Alarm Testing12/20/200512/21/200512/21/2005AFAIL
DetailsForrest France
A door has been added from the assembly area to the storage room disrupting the occupancy separation, this area will now require connection to the voice evac. and visual notification as well. No inspection until plans have been resubmitted and approved with required changes reflecting correct floor plan as installed.
Issue and Print Permit  12/9/2005 DONE
Alarm Plan Check  12/8/2005 PASS
Approved pending field inspection of fire alarm permit comments.
PLANS/APPL TAKEN TO FRONT DESK  12/8/2005 DONE
Permit Ready to Issue  12/8/2005 DONE
Inspection Record Card- Fire12/8/2005 12/8/2005 DONE
Telephone call  12/8/2005 DONE
Spoke with Dave and told him that permit is ready & fees///12/08/05 @8:15am BAS
Plan assigned to (Mary)10/7/2005 12/8/2005 DONE
Alarm Plan Check  11/30/2005 FAIL
Resubmittal required. Faxed comments to Rick Groom.
Plan resubmittals received  11/30/2005 DONE
Plan resubmittals received  11/10/2005 DONE
Case Summary  11/10/2005 DONE
Alarm Plan Check  10/18/2005 FAIL
Fire alarm system must be extended into the B and S1 areas because the separation requriement is 3 hours (S1 to A) with fire sprinkler reduction of 1 hour, a 2 hours wall is required. Only a 1 hour wall is being constructed. Horn/strobes are acceptable in the B and S1 areas.
Case Summary  10/7/2005 DONE
Case Summary  10/7/2005 DONE