INSP-Final Inspection | 4/4/2006 | 4/4/2006 | 4/4/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Issue and Print Permit | | | 2/27/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 2/24/2006 | | 2/24/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 10/7/2005 | | 2/23/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 2/23/2006 | | PASS |
|
|
|
Approved pending PDS Fire Inspector field verification. No comments written.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/23/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/23/2006 | | 2/23/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/23/2006 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 2/9/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/7/2006 | | DONE |
|
|
|
Spoke with Charlie, we are waiting on the UPS power information. SCP has decided to simply upgrade the FACP batteries to 24 hour stand-by. charlie will be resubmitting.
|
Plan resubmittals received | | | 12/8/2005 | | |
|
|
|
|
Telephone call | | | 10/18/2005 | | DONE |
|
|
|
Phoned Charlie Bayne, requested the circuit number so we can verify the EOL voltage after the appliance is relocated. He will e-mail the information to me.
|
Application received | | | 10/7/2005 | | |
|
|
|
|
Case Summary | | | 10/7/2005 | | DONE |
|
|
|
|