INSP-Final Inspection | 1/9/2007 | 1/9/2007 | 1/9/2007 | A | PASS |
Forrest France
|
|
|
Corrections are complete, final fire sprinkler inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2007 | 1/8/2007 | 1/8/2007 | P | PART |
Forrest France
|
|
|
OH hydro passed, noted missing bell sign, head box, signage at the riser room door, the main drain must be piped outside.
|
INSP-Supply line flush | 12/11/2006 | 12/12/2006 | 12/12/2006 | A | PART |
Forrest France
|
|
|
UG fire service supply line flush completed.
|
INSP-Supply line flush | 12/4/2006 | 12/4/2006 | 12/4/2006 | P | PART |
Forrest France
|
|
|
UG supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 7/12/2006 | 7/12/2006 | 7/12/2006 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed. Sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/30/2006 | 5/30/2006 | 5/30/2006 | P | PASS |
Troy Cobbley
|
|
|
OK to cover.
Scheduled by a contractor via Hello! on 5/30/2006 at 4:56:40 AM. Contact: ###-####.
|
Sprinkler Plan Check | 3/28/2006 | | 4/18/2006 | | PASS |
Bill Alexander
|
|
|
Revised calculations due to major underground supply changes in underground permit FIR05-00787.
|
Miscellaneous action | | | 4/18/2006 | | DONE |
|
|
|
Took approved permit documents to permit desk for returning.
|
Plan resubmittals received | | | 3/28/2006 | | DONE |
|
|
|
|
Issue permit | | | 11/14/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/10/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/10/2005 | | 11/10/2005 | | DONE |
|
|
|
|
Telephone call | | | 11/10/2005 | | DONE |
|
|
|
Left message for Tom that permit is ready & fees//11/10/05 9:20am BAS
|
Plan assigned to (Bill) | 10/20/2005 | | 11/9/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/20/2005 | | 11/9/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2005 | | DONE |
|
|
|
|
Application received | | | 10/20/2005 | | |
|
|
|
|