Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR05-00709
StatusFinaled
Name IDAHO FIRE PROTECTION
Site Address 2909 W CANAL ST
Project NameSPR JEMS TRIPLEX BLDG #5
Customer Number 
ePlanReview 
Description
(JEMS PROPERTIES TRIPLEX BUILDING #5 - APT #101, 201, 301) To install a fire life safety NFPA 13R system to prevent flashover (total involvement) in the room of fire origin, where sprinklered, and to improve the chance for occupants to escape/evacuated required for building "story" increase per the 2000 IBC, in a new 3,375-ft/2 three story, triplex. This work does not include the underground supply. Separate permit required for fire service underground with multiple lead-in work. The first floor is two bedrooms and two baths, at 1,186-ft/2, the second floor is two bedrooms and two baths with a 1,186-ft/2 and the third floor is one bedroom and one bath with 816-ft/2. System shall be equipped with an alarm initiating device connected to an alarm system and an outside annunciating devise. All fire sprinkler work and related, which includes dual service underground water supply, the system backflow prevention device (provided by others), shall be per NFPA 13R, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is attached to: BLD05-00807.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/9/20071/9/20071/9/2007APASS
DetailsForrest France
The required corrections have been completed, final inspection passed, permit finaled.
INSP-Final Inspection1/8/20071/8/20071/8/2007PNR
DetailsForrest France
derrick - fire life safety ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Hydro test failed, some items not complete for final.
INSP-Sprinkler Rough-in/Hydro1/8/20071/8/20071/8/2007PFAIL
DetailsForrest France
AG hydro failed due to visible leakage at the riser manifold.
INSP-Supply line flush12/11/200612/12/200612/12/2006APART
DetailsForrest France
UG fire supply line flush performed satisfactory.
INSP-Supply line flush12/4/200612/4/200612/4/2006PPART
DetailsForrest France
UG hydrostatic test of the supply line passed.
Sprinkler Plan Check3/28/2006 4/18/2006 PASS
DetailsBill Alexander
Revised calculations due to major underground supply changes in underground permit FIR05-00787.
Miscellaneous action  4/18/2006 DONE
Took approved permit documents to permit desk for returning.
INSP-Sprinkler Rough-in/Hydro4/13/20064/13/20064/13/2006APART
DetailsForrest France
Overhead rough-in corrections have been made, 3rd floor is acceptable for cover.
INSP-Sprinkler Rough-in/Hydro4/12/20064/12/20064/13/2006PDEFR
DetailsForrest France
Scheduled by a contractor via Hello! on 4/12/2006 at 8:51:23 AM. Contact: ###-####. Inspection to be completed 4/13.
Plan resubmittals received  3/28/2006 DONE
DetailsBill Alexander
INSP-Sprinkler Rough-in/Hydro2/27/20062/27/20062/27/2006PPART
DetailsForrest France
The 1st and 2nd floors only are good for rough-in cover, the third floor needs a tenting inspection for cold cavity protection prior to approval for cover, also two heads at the living room and hall (3rd floor) do not meet min. spacing requirements for these heads.
Inspection Record Card- Fire11/14/2005 11/14/2005 DONE
Issue permit  11/14/2005  
Plan assigned to (Bill)10/20/2005 11/9/2005 DONE
Sprinkler Plan Check10/20/2005 11/9/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  11/9/2005 DONE
Application received  10/20/2005