INSP-Final Inspection | 1/9/2007 | 1/9/2007 | 1/9/2007 | A | PASS |
Forrest France
|
|
|
Items on previous c/n are finished, fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2007 | 1/8/2007 | 1/8/2007 | P | PART |
Forrest France
|
|
|
Overhead hydro test passed, noted items missing for final including main drain, riser signage, head box, reliable heat for the riser room, etc.
|
INSP-Final Inspection | 1/8/2007 | 1/8/2007 | 1/8/2007 | P | CANC |
Forrest France
|
|
|
Duplicate inspection request.
|
INSP-Supply line flush | 12/11/2006 | 12/12/2006 | 12/12/2006 | A | PART |
Forrest France
|
|
|
Fire service supply line flush completed.
|
INSP-Supply line flush | 12/4/2006 | 12/4/2006 | 12/4/2006 | P | PART |
Forrest France
|
|
|
UG hydrostatic test of the fire supply line passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2006 | 5/1/2006 | 5/2/2006 | P | PART |
Forrest France
|
|
|
Third floor is approved for cover, insulation at one area repaired while on site, missing nailer plate has been installed.
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2006 | 5/3/2006 | 5/1/2006 | P | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/1/2006 at 8:32:15 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on May 1 2006 8:36AM.
|
Sprinkler Plan Check | 3/28/2006 | | 4/18/2006 | | PASS |
Bill Alexander
|
|
|
Revised calculations due to major underground supply changes in underground permit FIR05-00787.
|
Miscellaneous action | | | 4/18/2006 | | DONE |
|
|
|
Took approved permit documents to permit desk for returning.
|
Plan resubmittals received | | | 3/28/2006 | | DONE |
Bill Alexander
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2006 | 3/15/2006 | 3/15/2006 | A | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover at the 1st and 2nd floors only, 3rd floor inspected but not approved for cover until cold cavity protection has been installed and verified, missing nailer plate at third floor low wall main.
|
Issue permit | | | 11/14/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/10/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/10/2005 | | 11/10/2005 | | DONE |
|
|
|
|
Telephone call | | | 11/10/2005 | | DONE |
|
|
|
Left message for Tom that permit is ready & fees//11/10/05 9:20am BAS
|
Plan assigned to (Bill) | 10/20/2005 | | 11/9/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/20/2005 | | 11/9/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2005 | | DONE |
|
|
|
|
Application received | | | 10/20/2005 | | |
|
|
|
|