Permit Information
Permit NumberFIR05-00713
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 815 W ANN MORRISON PARK DR
Project NameCHARLIE FROG SCHOOLS
Customer Number 
ePlanReview 
Description
(CHARLIE FROG SCHOOLS-PRE SCHOOL & DAYCARE) To install a complete wet pipe, light hazard fire sprinkler system in a remodeled 10,134-ft/2, Type V-B, one story existing shell building for preschool & unfinished future tenant use. Daycare space will have 6,997-ft/2. Future space is 3,137-ft/2. This permit includes underground fire service supply, attached in S. Lois Ave., running north with approximately 20'-0" 6" C-900 Class 50 PVC under the footing and up through the floor with 6" Ductile Iron to approximately 6" with an M.J. Adapter. Fire sprinklers used for area. The future tenant space will require separate plans and permits. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-00713.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/27/20067/27/20067/28/2006PPASS
DetailsForrest France
Corrections have been completed, fire sprinkler permit finaled.
INSP-Final Inspection7/26/20067/26/20067/26/2006PPART
DetailsForrest France
Forward flow test performed satisfactory, need to provide NFPA 25, noted one fitting is leaking above childrens restroom-to be repaired prior to final.
INSP-Final Inspection7/24/20067/24/20067/24/2006PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 7/24/2006 at 9:26:31 AM. Contact: ###-####.
INSP-Final Inspection7/17/20067/17/20067/18/2006PPART
DetailsForrest France
Necessary corrections have been completed, final pending alarm testing at riser, forward flow.
INSP-Final Inspection7/11/20067/12/20067/13/2006ACANC
DetailsTroy Cobbley
roy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
INSP-Final Inspection7/10/20067/10/20067/10/2006PPART
DetailsForrest France
Items on previous correction notice have been addressed, need to attatch unistrut hangers to structure with an approved method above two rooms at the west side, heads at west room are overspaced off one wall, verify heads in the skylights are the proper temp. rating, wall at the storage room east side will require sheetrock to maintain proper separation between upright heads.
INSP-Final Inspection6/29/20066/30/20066/30/2006PFAIL
DetailsForrest France
Several items need correction, project is not ready for final inspection at this time. Preliminary rough-in inspection completed today addressing items such as incorrect hangers, spacing, head temps, seismic bracing and clearance, riser and plans which do not match installation- See 10 item correction notice left on site for review of a partial list of defficiencies. C/N does not constitute a complete listing of all issues regarding fire sprinklers at this time.
INSP-Sprinkler Rough-in/Hydro6/27/20066/28/20066/28/2006APART
DetailsForrest France
AG hydrostatic test completed.
INSP-Sprinkler Rough-in/Hydro6/26/20066/27/20066/27/2006AFAIL
DetailsForrest France
AG hydro failed due to visible leakage at two locations not repaired from the previous inspection. UG hydrostatic test is satisfactory.
INSP-Sprinkler Rough-in/Hydro6/26/20066/26/20066/26/2006PFAIL
DetailsForrest France
Visible leakage at three locations observed on the overhead system during hydrostatic test.
INSP-Supply line flush6/20/20066/21/20066/21/2006APART
DetailsForrest France
UG fire supply line flush performed satisfactory.
INSP-Sprinkler Rough-in6/16/20066/19/20066/19/2006APART
DetailsForrest France
UG supply line and riser are okay to cover, need to provide means for seismic clearance where ductile will pass through the floor slab.
CHANGE STATUS TO (ISS)  5/4/2006 DONE
per Sam Rogers ok to open permit.
Case Summary  4/25/2006  
Permit VOIDED4/21/20064/21/20064/21/2006 DONE
THIS PERMIT HAS BEEN VOID TO CANCELLING PER COMMERICAL FIRE 4/21/2006
INSP-Conference3/13/20063/16/20063/16/2006PCANC
DetailsForrest France
anita leatham; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ///cancelled per Anita w/Charlie Frog 3/16/06 10:06am LEG// Inspection cancelled from web by: Letitia Mesa
Issue permit  11/15/2005 DONE
Inspection Record Card- Fire11/14/2005 11/14/2005 DONE
Permit Ready to Issue  11/14/2005  
Telephone call  11/14/2005 DONE
left mess that permit is ready
Plan assigned to (Bill)10/21/2005 11/11/2005 DONE
Sprinkler Plan Check10/21/2005 11/11/2005 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  11/11/2005 DONE
Case Summary  10/21/2005 DONE
Application received  10/21/2005