INSP-Final Inspection | 9/7/2006 | 9/8/2006 | 9/8/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Contractor needs to install head guards on the sidewall heads
|
INSP-Sprinkler Rough-in | 2/17/2006 | 2/21/2006 | 2/21/2006 | A | PART |
Forrest France
|
|
|
Changes at two locations for the overhead rough-in at the deleted closet and added sw are acceptable, RI good for cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2006 | 2/13/2006 | 2/13/2006 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. Per contractor the sprinkler head that is missing in the closet will not be required since shelving extends to the door. To be verified when installed.
|
INSP-Sprinkler Rough-in | 2/8/2006 | 2/9/2006 | 2/9/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need head installed in the master closet as shown on the approved plans.
|
Telephone call | | | 2/9/2006 | | DONE |
|
|
|
gave paperwork to customer no fee charged for 2nd review
|
Plan resubmittals received | | | 2/8/2006 | | |
|
|
|
|
Issue and Print Permit | | | 11/18/2005 | | |
|
|
|
|
Plan assigned to (Bill) | 10/24/2005 | | 11/17/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/17/2005 | | 11/17/2005 | | PASS |
Troy Cobbley
|
|
|
Plans approved as noted. No written comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/17/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/17/2005 | | 11/17/2005 | | DONE |
|
|
|
|
Telephone call | | | 11/17/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Case Summary | | | 10/24/2005 | | |
|
|
|
|
Application received | | | 10/24/2005 | | |
|
|
|
|