IDAHO EDUCATION ASSOCIATION * To install a complete underground fire service supply and overhead wet, grid, Light Hazard occupancy fire sprinkler system in an existing 15,690-ft/2 two-story building. The underground supply includes approximately 40'-0" of 6" C-900 PVC which offsets into a north east (unidentified) room of this building thought a wall with 6" approved ferrous pipe (not identified). Each floor consists of 7,845-ft/2. This building will be fully fire sprinklered under this permit. Fire sprinklers is for area and story to A-3 basic allowable increases, the allowance of non-rated exit corridors, the allowance for unenclosed exit stairways, and non-rated mechanical/boiler room. (The mechanical/boiler room, however, is a sprinklered incidental use area and is to be smoke tight construction with full height walls, self-closing smoke sealed doors, and smoke dampers at any duct penetrations). All fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-01295.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary  10/23/2012 DONE
INSP-Final Inspection2/5/20072/6/20072/5/2007APASS
DetailsTroy Cobbley
Fire sprinkler permit finaled.
INSP-Sprinkler Rough-in12/15/200612/15/200612/15/2006PPASS
DetailsForrest France
Previous c/n items have been completed, final inspection passed, permit okay to final.
INSP-Final Inspection12/12/200612/13/200612/14/2006AFAIL
DetailsForrest France
Missing automatic ball drip at the FDC, missing seismic bracing at the basement level 2.5" main as noted, escutcheons need to be installed at some locations.
INSP-Sprinkler Rough-in/Hydro6/1/20066/2/20066/2/2006APART
DetailsForrest France
UG hydrostatic test and overhead hydrostatic test for the two AG systems performed satisfactory.
INSP-Supply line flush5/31/20066/1/20066/2/2006PPART
DetailsForrest France
UG supply line flush performed satisfactory.
Plan assigned to (Bill)2/23/2006 3/20/2006 DONE
DetailsBill Alexander
Sprinkler Plan Check2/23/2006 3/20/2006 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  3/20/2006 DONE
Permit Ready to Issue  3/20/2006  
Inspection Record Card- Fire3/20/2006 3/20/2006 DONE
Telephone call  3/20/2006  
Left message with Jeff Anderson (Treasure Valley Fire Protection Inc) ###-#### to pick up permit 3-20-06 eus
CHANGE STATUS TO (ISS)  3/20/2006  
(F) Reprint permit  3/20/2006 DONE
Plan resubmittals received  2/23/2006 DONE
Permit Ready to Issue  1/20/2006 DONE
Telephone call  1/20/2006 DONE
left mess that permit is ready
CHANGE STATUS TO (ISS)  1/20/2006 DONE
(F) Reprint permit  1/20/2006 DONE
Sprinkler Plan Check12/30/2005 1/19/2006 PART
DetailsBill Alexander
The data has been moved to a Word document attached to this case.
Plan assigned to (Bill)10/31/2005 1/19/2006 DONE
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  1/19/2006 DONE
Plan resubmittals received  12/30/2005  
INSP-Sprinkler Rough-in12/22/200512/22/200512/22/2005PPART
DetailsForrest France
UG fire supply line is acceptable to cover.
CHANGE STATUS TO (ISS)  12/22/2005 DONE
already pd for
Sprinkler Plan Check12/7/2005 12/21/2005 FAIL
DetailsTroy Cobbley
Plans failed. Review comments and phone call to Jeff Anderson at Treasure Valley Fire
PLANS/APPL TAKEN TO FRONT DESK  12/21/2005 DONE
Telephone call  12/21/2005 DONE
called ###-#### and told Jeff that plans failed and need to pick up plans
Plan resubmittals received  12/7/2005  
Issue and Print Permit  12/1/2005  
Sprinkler Plan Check11/30/2005 11/30/2005 FAIL
DetailsTroy Cobbley
Contractor was given a partial approval. OK to begin work per review comments. Review comments faxed to contractor.
PLANS/APPL TAKEN TO FRONT DESK  11/30/2005 DONE
Permit Ready to Issue  11/30/2005 DONE
Inspection Record Card- Fire11/30/2005 11/30/2005 DONE
Telephone call  11/30/2005 DONE
left mess that permit is ready
Miscellaneous action  11/16/2005 DONE
approved a written early start request for this project.
Application received  10/31/2005