INSP-Final Inspection | 2/2/2007 | 2/5/2007 | 2/5/2007 | P | PASS |
Forrest France
|
|
|
Items on previous correction notice have been verified for compliance, final fire sprinkler inspection passed, permit finaled.
|
INSP-Final Inspection | 2/1/2007 | 2/2/2007 | 2/2/2007 | A | CANC |
Forrest France
|
|
|
Mike Bierman is the contact @ ###-####. Thank you Phone #: ###-####
|
INSP-Final Inspection | 1/31/2007 | 2/1/2007 | 1/31/2007 | A | FAIL |
Forrest France
|
|
|
Need to adjust the tamper switch at the PIV, provide pendent heads in the head box, attatch "911" sign at the outside bell, dry system #2 exceeds allowable trip time per NFPA for the system size (water was delivered to the test connection at 1min. 30 sec.).
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2007 | 1/18/2007 | 1/18/2007 | A | PART |
Forrest France
|
|
|
System 1 and 2 passed 24 hr. air test, pressure loss at system 2 was within the allowable 1 1/2 psi per NFPA 13.
|
INSP-Sprinkler Rough-in | 1/16/2007 | 1/17/2007 | 1/17/2007 | A | PART |
Forrest France
|
|
|
Begin 24 hr. air test at 10:00 am, start psi. at system 2 is 40.5, system 1 is 40 psi.
|
INSP-Sprinkler Rough-in/Hydro | 1/15/2007 | 1/16/2007 | 1/16/2007 | A | FAIL |
Forrest France
|
|
|
Air test failed due to start pressures below the min. amount allowed per NFPA 13.
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2006 | 12/18/2006 | 12/18/2006 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing for the two dry systems and the single wet system passed. Also approved the rough-in installation for cover at the office area. Still need to perform 24 hr. air test on the dry systems per NFPA, noted missing flex couplings at the riser and provision for forward flow testing of the BFP.
|
INSP-Supply line flush | 12/13/2006 | 12/14/2006 | 12/14/2006 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed.
|
INSP-Supply line flush | 12/7/2006 | 12/8/2006 | 12/8/2006 | A | FAIL |
Forrest France
|
|
|
Inspection for the UG fire supply line flush was not completed due to lack of sufficient water flow. Noted the yard PIV was not operating correctly and is installed below allowable 36" height above grade.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2006 | 10/20/2006 | 10/20/2006 | P | PART |
Forrest France
|
|
|
UG fire supply line hydro test is satisfactory.
|
INSP-Sprinkler Rough-in | 10/18/2006 | 10/18/2006 | 10/18/2006 | P | PART |
Forrest France
|
|
|
UG fire supply line is okay to cover, need as-builts reflecting yard PIV installation.
|
Permit Ready to Issue | | | 7/27/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/27/2006 | | DONE |
|
|
|
spoke to trent@###-####/told permit was ready, permit#, address, project name, and fee
|
Issue and Print Permit | | | 7/27/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 6/5/2006 | | 7/26/2006 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 7/18/2006 | | 7/26/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/18/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/12/2006 | | DONE |
|
|
|
spoke to trent@###-####/told insp failed and can be picked up
|
Telephone call | | | 7/12/2006 | | DONE |
|
|
|
gave plans to customer with shilo plans failed
|
Sprinkler Plan Check | 7/5/2006 | | 7/11/2006 | | FAIL |
Bill Alexander
|
|
|
Re-Submittals Of The Following Items Are Required:
1. Plan submittal is unacceptable since they do not meet minimum requirements of IFC 105.4.2 and BMC 7-01-53-IFC 901.2.
a. Provide full size plans that are scaled and completely legible with minimum 10 point fonts [depending on the plan background cleanliness]),
b. Includes required sections that show elevations of ceiling/s, piping, etc.,
c. Modified riser detail with added wet system that includes all appurtenances/devices;
d. Hangers (include types, locations),
e. Head legend with all manufacturers models and SINumbers installing (uprights adding are not identified),
f. Location of required drain/s, etc.
g. Include areas that will be on the wet system and areas on the dry system, with the dry system number identified.
|
Plan resubmittals received | | | 7/5/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/27/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/26/2006 | | 6/27/2006 | | PASS |
Bill Alexander
|
|
|
|
Telephone call | | | 6/27/2006 | | DONE |
|
|
|
spoke to lilly@###-####/told permit was ready and no fees
|
Telephone call | | | 6/27/2006 | | DONE |
|
|
|
gave plans to customer no fee due per bill a.
|
INSP-Sprinkler Rough-in | 6/15/2006 | 6/16/2006 | 6/16/2006 | A | PART |
Forrest France
|
|
|
UG fire supply line riser and stub-out appears satisfactory, no approved plans on site for verification of pipe size, etc., need to provide means for seismic clearance where the ductile riser will pass through floor slab, need to cover open ended MJ x flange adaptor at riser piece.
|
Plan assigned to (Bill) | 11/8/2005 | | 12/8/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/8/2005 | | 12/8/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/8/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/8/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Inspection Record Card- Fire | 12/8/2005 | | 12/8/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/8/2005 | | DONE |
|
|
|
|
Miscellaneous action | | | 12/7/2005 | | DONE |
|
|
|
9:15am-Trent Bice requested this review be moved to the line of Alpine Real Estate T.I. FIR05-00781 and Alpine Real Estate be moved in place of FedEx Distributin Center.
|
Case Summary | | | 11/8/2005 | | DONE |
|
|
|
|
Application received | | | 11/8/2005 | | |
|
|
|
|