INSP-Final Inspection | 1/6/2006 | 1/6/2006 | 1/6/2006 | A | PASS |
Forrest France
|
|
|
Corrections have been made, fire sprinkler finaled.
|
INSP-Final Inspection | 1/5/2006 | 1/5/2006 | 1/5/2006 | P | PART |
Forrest France
|
|
|
Items on c/n are complete, two painted heads in the confrence room will need to be replaced prior to final.
|
INSP-Final Inspection | 12/1/2005 | 12/1/2005 | 12/2/2005 | P | FAIL |
Forrest France
|
|
|
Missing coverage at stair landing 1st level, ssu under stairs is partially blocked, need ceiling and canopies installed at two areas, the remainder of rough-in for this permit is okay.
|
INSP-Final Inspection | 11/29/2005 | 11/30/2005 | 11/30/2005 | P | CANC |
Forrest France
|
|
|
Inspection to be conducted tomorrow per conversation with contractor.
|
Issue permit | | | 11/16/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/14/2005 | | 11/14/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/14/2005 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 11/9/2005 | | 11/11/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/9/2005 | | 11/11/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/11/2005 | | DONE |
|
|
|
|
Case Summary | | | 11/11/2005 | | DONE |
|
|
|
|
Application received | | | 11/9/2005 | | |
|
|
|
|