INSP-Final Inspection | 3/26/2010 | 3/26/2010 | 3/26/2010 | P | PASS |
Forrest France
|
|
|
Underground fire supply line permit final approved.
|
INSP-Conference | 3/26/2010 | 3/26/2010 | 3/26/2010 | P | DONE |
Forrest France
|
|
|
Regarding permit status and conditions on parcel hold for this address.
|
Miscellaneous action | | | 3/12/2010 | | DONE |
|
|
|
Sent email requesting project status.
|
INSP-Supply line flush | 12/12/2006 | 12/12/2006 | 12/13/2006 | P | PART |
Forrest France
|
|
|
UG supply line flush completed satisfactory.
|
INSP-Supply line flush | 5/16/2006 | 5/17/2006 | 5/17/2006 | A | PART |
Forrest France
|
|
|
UG fire supply lines are good for cover, will need to provide means for seismic clearance where the riser pipe passes through the floor slab, pipe is required to be bedded before backfill.
|
CHANGE STATUS TO (ISS) | | | 4/20/2006 | | |
|
|
|
no fee plans picked up
|
(F) Reprint permit | | | 4/20/2006 | | |
|
|
|
|
Sprinkler Plan Check | 3/28/2006 | | 4/18/2006 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 4/18/2006 | | 4/18/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/18/2006 | | DONE |
|
|
|
lft vm with tom dutkus ###-#### that permit is ready to be picked up and no fees
|
Plan resubmittals received | | | 3/28/2006 | | |
|
|
|
|
Issue and Print Permit | | | 1/20/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 11/15/2005 | | 12/12/2005 | | |
|
|
|
|
Sprinkler Plan Check | 11/15/2005 | | 12/12/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/12/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/12/2005 | | 12/12/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/12/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/12/2005 | | DONE |
|
|
|
called ###-#### and left message that permit is ready and fees
|
Case Summary | | | 11/15/2005 | | |
|
|
|
|
Application received | | | 11/15/2005 | | |
|
|
|
|