INSP-Final Inspection | 5/29/2007 | 5/30/2007 | 5/30/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 5/24/2007 | 5/25/2007 | 5/25/2007 | A | DEFR |
Forrest France
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
INSP-Final Inspection | 5/23/2007 | 5/24/2007 | 5/24/2007 | A | PART |
Forrest France
|
|
|
Per field inspection by M. Timmerman, need verification of the dry system capacity prior to final acceptance.
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2007 | 5/23/2007 | 5/23/2007 | P | PART |
Forrest France
|
|
|
Dry system air test passed within the allowable leakage amount, system lost 1/2 psi over 24 hrs.
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2007 | 5/22/2007 | 5/22/2007 | P | PASS |
Troy Cobbley
|
|
|
The above ground and under ground hydro tests passed. The 24 hour air test was started at 1:30 with 43 psi showing on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2007 | 5/17/2007 | 5/17/2007 | A | FAIL |
Troy Cobbley
|
|
|
The overhead hydro was started but is now failed because the riser room door is locked and nobody seems to be able to find a key.
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2007 | 5/16/2007 | 5/16/2007 | P | DEFR |
Forrest France
|
|
|
Inspection rescheduled.
|
INSP-Sprinkler Rough-in | 5/1/2007 | 5/2/2007 | 5/2/2007 | A | PASS |
Troy Cobbley
|
|
|
Items listed on the plans have been corrected.
|
INSP-Sprinkler Rough-in | 4/25/2007 | 4/25/2007 | 4/25/2007 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations of inspection and for corrections required.
|
INSP-Sprinkler Rough-in | 4/23/2007 | 4/24/2007 | 4/24/2007 | A | FAIL |
Troy Cobbley
|
|
|
I was told I was not supposed to be in the building by who appears to be a flooring guy. No inspection performed
|
INSP-Sprinkler Rough-in | 2/13/2007 | 2/13/2007 | 2/13/2007 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the piping locations that are ok to cover
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/31/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/31/2007 | | DONE |
|
|
|
tlk Jim Darr ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 1/31/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/31/2007 | | 1/31/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/31/2007 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 1/22/2007 | | 1/31/2007 | | PASS |
|
|
|
1/31/2007 10:03:22 CMC - activity updated through activity FIRA22 from case FIR05-00822.
|
Sprinkler Plan Check | 1/26/2007 | | 1/29/2007 | | PASS |
|
|
|
Plans review by Bryan Johnson *As built plans are approved as submitted
|
Plan resubmittals received | | | 1/22/2007 | | DONE |
|
|
|
Changed REV per Scott A///1/22/07 BAS
|
INSP-Conference | 1/5/2007 | 1/5/2007 | 1/5/2007 | P | CANC |
Troy Cobbley
|
|
|
Conference would have been for items that I dont inspect for
|
INSP-Sprinkler Rough-in | 12/6/2006 | 12/7/2006 | 12/7/2006 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping under the balcony is ok to cover
|
Telephone call | | | 5/5/2006 | | DONE |
|
|
|
tlk to jeff anderson ###-####8 that permit and fees are ready to be picked up
|
Override - Parcel Holds | | | 5/5/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 5/5/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/5/2006 | | |
|
|
|
|
Issue and Print Permit | | | 5/5/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/4/2006 | | 5/4/2006 | | PASS |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 4/27/2006 | | 5/4/2006 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2006 | | DONE |
|
|
|
|
FIR-Aging Inspection | 5/1/2006 | 5/1/2006 | 5/2/2006 | | NR |
Troy Cobbley
|
|
|
work in progess. resubmittals received last week
|
Plan resubmittals received | | | 4/26/2006 | | |
|
|
|
|
Sprinkler Plan Check | 1/5/2006 | | 1/30/2006 | | PART |
Bill Alexander
|
|
|
The data has been moved to a Word document attached to this case.
|
Plan assigned to (Bill) | 12/1/2005 | | 1/30/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/30/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 1/30/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/30/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 1/30/2006 | | 1/30/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/30/2006 | | |
|
|
|
|
Issue and Print Permit | | | 1/30/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/24/2006 | | DONE |
|
|
|
Talked to John Venche (designer) requesting information starting with the basics:
1. Where is the riser actually located and the dry and wet mains appear connected?
2. Dry system capacity not provided.
3. Why was the system design areas verified with different water supply information (document)?
4. Why is a portion of the building system that is inside of this building, on the dry system?
Stopped review due to too many variables.
|
Miscellaneous action | | | 1/24/2006 | | DONE |
|
|
|
Email received from john Venche requesting to wait till tomorrow for the actual desinger (from Twin Falls) arrives to go over the plans.
|
Plan resubmittals received | | | 1/5/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/1/2005 | | 12/16/2005 | | FAIL |
Troy Cobbley
|
|
|
Per phone converstion relating to design deficiencies throughout. New plan resubmittal required.
|
Application received | | | 12/1/2005 | | |
|
|
|
|
Case Summary | | | 12/1/2005 | | DONE |
|
|
|
|