INSP-Final Inspection | 3/6/2006 | 3/6/2006 | 3/6/2006 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2006 | 3/6/2006 | 3/6/2006 | A | PASS |
Troy Cobbley
|
|
|
Inspection was for final not rough-in. Permit finaled.
|
INSP-Sprinkler Rough-in | 2/16/2006 | 2/17/2006 | 2/17/2006 | A | FAIL |
Forrest France
|
|
|
Heads are not cut in at any location for verification of spacing or installation method, the "work room" designated as OTS will require a drop ceiling or provide upright sprinkler protection for the entire space/cavity above all ceiling areas.
|
Issue and Print Permit | | | 12/20/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/16/2005 | | 12/16/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/16/2005 | | |
|
|
|
|
Telephone call | | | 12/16/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (Bill) | 12/1/2005 | | 12/16/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/1/2005 | | 12/16/2005 | | PASS |
|
|
|
Approved with no written comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2005 | | DONE |
|
|
|
|
Application received | | | 12/1/2005 | | |
|
|
|
|
Inspection Record Card- Fire | 12/16/2005 | | | | |
|
|
|
|