INSP-Final Inspection | 9/16/2008 | 9/16/2008 | 9/16/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/14/2006 | 12/14/2006 | 12/15/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given on this fire alarm permit until the 2nd floor NAC panel has been tested and the as-built fire alarm plans have been resubmitted.
|
INSP-Final Inspection | 12/11/2006 | 12/11/2006 | 12/12/2006 | P | FAIL |
Troy Cobbley
|
|
|
Waiting for the second floor NAC panel's new card to be installed and the interconnection with the FACP to be tested.
|
INSP-Final Inspection | 12/7/2006 | 12/8/2006 | 12/8/2006 | P | FAIL |
Troy Cobbley
|
|
|
See city approved plans for induct detectors tested. 17 inducts tested.
|
INSP-Final Inspection | 12/7/2006 | 12/7/2006 | 12/7/2006 | P | FAIL |
Troy Cobbley
|
|
|
Finished testing the fire alarm connections for this permit which included jockey pump tamper, tank supply tamper, tank fill tamper and the first floor tamper and flow switch. Inspection was stopped when the first duct smoke detector inspected had the sample tube pointing the wrong way.
|
INSP-Final Inspection | 12/6/2006 | 12/6/2006 | 12/6/2006 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the pharmacy for devices tested. All of the notification devices have been tested. See the approved plans for locateions where a 15 and a 75 need swapped. I stopped the inspection due to time constraints and upon finding a duct smoke detector missing the plug in the sample tube and it shut the smoke damper. Also multiple smoke detectors still had tape on them and a/v's still had tape and paper covering them or were missing covers. I found one junction box at the failed duct detector that was missing its cover and had wiring spilling from it. I found one manual pull station at the east exit that was not attached to the wall.
|
FIR-Aging Inspection | 6/22/2006 | 6/22/2006 | 6/23/2006 | | NR |
Troy Cobbley
|
|
|
Central tower work is in progress
|
Inspection Record Card- Fire | 3/13/2006 | | 3/13/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/13/2006 | | |
|
|
|
|
Issue and Print Permit | | | 3/13/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 3/12/2006 | | PASS |
|
|
|
A RESUBMITTAL WILL BE REQUIRED PRIOR TO FINAL INSPECTION.
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 3/10/2006 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Charlie Bayne.
|
Plan resubmittals received | | | 3/10/2006 | | DONE |
|
|
|
Received required resubmittal information via fax.
|
Plan resubmittals received | | | 2/27/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 12/14/2005 | | FAIL |
|
|
|
No written comments. I called Charlie Bayne from Simplex and stated that he could come down and mark up his set based on my comments. He stated he would be down.
|
Case Summary | | | 12/6/2005 | | DONE |
|
|
|
|
Application received | | | 12/6/2005 | | |
|
|
|
|
Plan assigned to (Mary) | 12/6/2005 | | | | |
|
|
|
|