INSP-Final Inspection | 5/23/2006 | 5/24/2006 | 5/24/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 5/22/2006 | 5/23/2006 | 5/23/2006 | A | FAIL |
Troy Cobbley
|
|
|
Forward flush failed.
|
INSP-Conference | 5/17/2006 | 5/17/2006 | 5/17/2006 | P | DONE |
Troy Cobbley
|
|
|
Correction notice left with Carolyn Mauer that all FIR permits to be finaled by 5-23-2006 or the school will be shutdown. I called Ken at AEI, Brad at SimplexGrinnell and left a message for Randy at DeBest about their permits needing finaled. I also contacted Dave Hanniman about what is going on.
|
INSP-Final Inspection | 5/5/2006 | 5/5/2006 | 5/5/2006 | P | FAIL |
Troy Cobbley
|
|
|
Repair the PIV tamper switch, insulate the underground in the crawl space, lower the FDC and provide through bolts for the EQ bracing.
|
FIR-Aging Inspection | 3/16/2006 | 3/16/2006 | 3/20/2006 | | NR |
Troy Cobbley
|
|
|
I spoke to Chris with SimplexGrinnell he is to follow up on status.
|
Issue and Print Permit | | | 12/15/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/14/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/14/2005 | | 12/14/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/14/2005 | | DONE |
|
|
|
Left voice message for Tom that told that permit is ready & fees///12/14/05 @ 8:26am BAS
|
Plan assigned to (Bill) | 12/12/2005 | | 12/13/2005 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/12/2005 | | 12/13/2005 | | PASS |
Bill Alexander
|
|
|
Field Verify redlined plans
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2005 | | DONE |
|
|
|
|
Case Summary | | | 12/12/2005 | | DONE |
|
|
|
|
Application received | | | 12/12/2005 | | |
|
|
|
|