INSP-Final Inspection | 4/4/2007 | 4/4/2007 | 4/4/2007 | P | PASS |
Forrest France
|
|
|
UG supply line permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 3/16/2007 | 3/16/2007 | 3/16/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2006 | 8/15/2006 | 8/16/2006 | P | CANC |
Forrest France
|
|
|
Wrong permit number requested for inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/13/2006 | 7/14/2006 | 7/14/2006 | A | FAIL |
Troy Cobbley
|
|
|
Arrived at job site to witness the underground hydro test but they were not ready.
|
INSP-Supply line flush | 6/29/2006 | 6/30/2006 | 6/30/2006 | A | PART |
Forrest France
|
|
|
UG supply line flush performed satisfactory.
|
INSP-Sprinkler Rough-in | 1/24/2006 | 1/25/2006 | 1/25/2006 | A | PART |
Forrest France
|
|
|
Approved plans were not available for review at the time of inspection (locked in job trailer), the installation of an 8" supply, ductile riser, and thrust block verified. Depth of bury and bedding is okay, need to provide seismic clearance method for the ductile riser at floor slab and protect the open riser pipe end from debris.
|
Inspection Record Card- Fire | 1/13/2006 | | 1/13/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/13/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/13/2006 | | DONE |
|
|
|
tlk to trent bice - ###-#### that permit and fees are ready to be picked up
|
Issue and Print Permit | | | 1/13/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 12/21/2005 | | 1/12/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/21/2005 | | 1/12/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2006 | | DONE |
|
|
|
|
Application received | | | 12/21/2005 | | |
|
|
|
|