INSP-Final Inspection | 4/24/2006 | 5/1/2006 | 5/1/2006 | A | PASS |
Forrest France
|
|
|
Vesda system functioned properly, fire alarm passed field inspection.
|
Alarm Plan Check | | | 3/10/2006 | | PASS |
|
|
|
Approved pending PDS Fire Inspector field verification. No comments written.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/10/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 1/20/2006 | | 3/10/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 2/24/2006 | | FAIL |
|
|
|
Resubmittal required. no provision for HVAC shutdown from the FA system based upon the smoke detector in the return of the HVAC unit.
|
Miscellaneous action | | | 2/16/2006 | | DONE |
|
|
|
Question back to MTI if a mechanical permit is required.
|
Case Summary | | | 2/13/2006 | | |
|
|
|
|
Application received | | | 1/20/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|