INSP-Final Inspection | 4/21/2006 | 4/24/2006 | 4/24/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 4/20/2006 | 4/21/2006 | 4/21/2006 | P | PART |
Forrest France
|
|
|
Hydrostatic test for the UG supply and the overhead system both passed inspection. Rough-in inspection is satisfactory as well, need to provide a ball drip at the FDC, and signage at the FDC per review notes.
|
INSP-Supply line flush | 4/12/2006 | 4/13/2006 | 4/13/2006 | A | PART |
Forrest France
|
|
|
UG supply line flush performed satisfactory, the PIV has been adjusted to the required height above finish grade.
|
INSP-Supply line flush | 4/7/2006 | 4/11/2006 | 4/11/2006 | P | DEFR |
Forrest France
|
|
|
No time available to complete this inspection today, to be rescheduled per conversation with contractor.
|
INSP-Sprinkler Rough-in | 3/27/2006 | 3/28/2006 | 3/28/2006 | A | FAIL |
Forrest France
|
|
|
The yard post indicator is below min. height requirements above finish grade, need to cap ductile riser piece, provide seismic clearance at floor slab. Thrust blocks are acceptable, the majority of UG pipe run was covered prior to inspection.
|
Sprinkler Plan Check | 2/23/2006 | | 3/17/2006 | | PASS |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 2/22/2006 | | 3/17/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/17/2006 | | |
|
|
|
Informed Curtis (Simplex/Grinnell) ###-#### to pick up permit 3-17-06 eus
|
Inspection Record Card- Fire | 3/17/2006 | | 3/17/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/17/2006 | | |
|
|
|
|
Issue and Print Permit | | | 3/17/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/23/2006 | | |
|
|
|
|
Issue and Print Permit | | | 2/15/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 1/20/2006 | | 2/9/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/20/2006 | | 2/9/2006 | | PART |
Bill Alexander
|
|
|
Corrections Required:
1. An exterior indicating control valve meeting minimum 13-8.1.2, 24-2.2.6, 6.3.1, 6.3.3.2 requirements, shall be provided for this facility. If this is not provided, then a 1 (one) hour fire rated construction sprinkler control room must be provided with an approved outside clear door access. All control valves on fire sprinkler systems must be unobstructed, immediately discernible and accessible. The control handles must be installed between two (2'-0") and five (5'-0") feet above finished grade. Post indicators shall be set so that the top of the post will be 36" above the final grade. (NFPA 13-8.15.1.3, IFC 102.7)
2. Designer submitted a Sammy® (Speedy Products) sheet addressing connections to TJI's. Plans do not reference any TJI's in the building? Connection to TJI's must meet the manufacturer's installation of the same which are limited as to hanger connections AND the pipe size supporting. Connections for seismic requirements are also reference in the manufacturer's installation guides. Designer shall provide correct clarification and details of the TJI's, the hanger connections and seismic attachments incorporating, which meet the manufacturer's requirements, on the plans. (BMC 7-01-50-901.2, IFC 105.4.2)
3. Provide correct dimensioning or and approved scale of the riser from the floor. (BMC 7-01-50 IFC 901.2, IFC 105.4.2)
4. It is assumed that all inside wall penetrations are through "frangible" walls. If not, then corrections addressing the wall locations and minimum penetration/flexible requirements shall be included on the plans. (NFPA 13-9.3.2*, 9.3.3*, A.9.3.3, A.9.3.2, 14.1.3 (21)
5. Designer must show type and location of all required, not required joints (flexible & ridgid) and fitting on the mains and lines. (BMC 7-01-50 IFC 901.2, IFC 105.4.2, NFPA 13-14.1.3 [21])
6. Provide size of city main in the street and whether it is dead-end or circulating. (NFPA 13-14.1.3 (10)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/9/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/9/2006 | | 2/9/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/9/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/9/2006 | | |
|
|
|
Left message forTom Easton ###-#### that permit is ready to be picked up
|
Plan resubmittals received | | | 1/31/2006 | | |
|
|
|
|
Application received | | | 1/20/2006 | | |
|
|
|
|
Case Summary | | | 1/20/2006 | | DONE |
|
|
|
|