INSP-Final Inspection | 12/28/2006 | 12/29/2006 | 12/29/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permitted work passed final inspection.
|
Issue and Print Permit | | | 12/11/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/1/2006 | | 12/7/2006 | | PASS |
|
|
|
Plan modifications reviewed/approved onsite by T. Cobbley 12/1/06; stamped by SLR 12/7.
|
Plan resubmittals received | | | 12/1/2006 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 8/22/2006 | 8/24/2006 | 8/25/2006 | A | PART |
Forrest France
|
|
|
Field inspection of phase two sprinkler rough-in of the project as marked on plans is satisfactory, heads to be installed below ductwork obstruction as discussed.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2006 | 6/26/2006 | 6/26/2006 | P | PART |
Forrest France
|
|
|
Overhead rough-in for phase one of the project as marked on approved plans is okay to cover.
|
CHANGE STATUS TO (ISS) | | | 6/20/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/20/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 1/30/2006 | | 1/30/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/27/2006 | | 1/30/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2006 | | DONE |
|
|
|
|
Application received | | | 1/26/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|