INSP-Final Inspection | 3/21/2007 | 3/22/2007 | 3/23/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 6/29/2006 | 6/29/2006 | 6/29/2006 | P | PASS |
Troy Cobbley
|
|
|
Supply line flush passed.
|
INSP-Sprinkler Rough-in | 3/22/2006 | 3/23/2006 | 3/23/2006 | P | PART |
Troy Cobbley
|
|
|
Underground supply is ok to cover up to city connection which will need to be inspected when completed.
|
Issue and Print Permit | | | 2/24/2006 | | |
|
|
|
|
Plan assigned to (Bill) | 2/2/2006 | | 2/21/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/2/2006 | | 2/21/2006 | | PASS |
Troy Cobbley
|
|
|
Approved as noted
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/21/2006 | | 2/21/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/21/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/21/2006 | | DONE |
|
|
|
left mess that permit is ready
|
Application received | | | 2/2/2006 | | |
|
|
|
|