INSP-Final Inspection | 7/6/2006 | 7/7/2006 | 7/7/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/8/2006 | 6/9/2006 | 6/9/2006 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test performed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2006 | 5/3/2006 | 5/3/2006 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover up to the engine bays. Underground hydro test and flush passed.
|
INSP-Supply line flush | 5/2/2006 | 5/3/2006 | 5/3/2006 | A | PASS |
Troy Cobbley
|
|
|
Supply line hydro test and flush passed.
|
Sprinkler Plan Check | 4/3/2006 | | 4/25/2006 | | PASS |
Bill Alexander
|
|
|
Incorproated pipe, head and design changes.
|
Miscellaneous action | | | 4/25/2006 | | DONE |
|
|
|
Took resubmittals (2nd submittals) to permit desk for relaeasing. No fees.
|
Inspection Record Card- Fire | 4/25/2006 | | 4/25/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/25/2006 | | |
|
|
|
called Gerald Ebeling fire permit ready to be picked up no added fees///DLD
|
Telephone call | | | 4/25/2006 | | DONE |
|
|
|
gave plans to customer
|
INSP-Sprinkler Rough-in | 4/4/2006 | 4/5/2006 | 4/5/2006 | A | PART |
Troy Cobbley
|
|
|
UG fire supply line is acceptable for cover.
|
Plan resubmittals received | | | 4/3/2006 | | |
|
|
|
|
Plan assigned to (Bill) | 2/3/2006 | | 2/23/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/3/2006 | | 2/23/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/23/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 2/23/2006 | | 2/23/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/23/2006 | | |
|
|
|
Informed Treasure Valley Fire Protection to pick up permit 2-23-06 eus
|
Issue and Print Permit | | | 2/23/2006 | | DONE |
|
|
|
|
Case Summary | | | 2/3/2006 | | DONE |
|
|
|
|
Application received | | | 2/3/2006 | | |
|
|
|
|