INSP-Final Inspection | 1/8/2007 | 1/10/2007 | 1/10/2007 | A | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2006 | 11/9/2006 | 11/9/2006 | A | PART |
Forrest France
|
|
|
The remainder of OH rough-in is good for cover as indicated on approved plans, final pending drop in ceiling installation.
|
Sprinkler Plan Check | | | 10/19/2006 | | PASS |
|
|
|
Rev#2-Plan modification reviewed/approved by T. Cobbley.
|
Issue and Print Permit | | | 7/21/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/14/2006 | | 7/17/2006 | | PASS |
Bill Alexander
|
|
|
Added 5 heads and relocated 2 existing for the protection of a created return air chase.
|
Plan assigned to (Bill) | 7/14/2006 | | 7/14/2006 | | DONE |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 7/14/2006 | | DONE |
Bill Alexander
|
|
|
Plan Modifications
|
INSP-Sprinkler Rough-in | 6/5/2006 | 6/12/2006 | 6/12/2006 | P | PART |
Forrest France
|
|
|
Inspection for overhead rough-in cover at the SW portion of the remodel and the return air duct as marked on plans is good for cover, approved plans reflecting field changes and actual installation to be on site prior to final. Also inspected heads below floor for cover as marked on plans.
|
INSP-Sprinkler Rough-in | 4/24/2006 | 4/27/2006 | 4/28/2006 | P | PART |
Forrest France
|
|
|
Partial inspection for sprinkler rough-in as marked on approved plans cleanroom only, noted missing retaining straps at two locations in the area inspected.
|
Issue and Print Permit | | | 2/23/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 2/14/2006 | | 2/22/2006 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 2/14/2006 | | 2/22/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/22/2006 | | DONE |
|
|
|
|
Application received | | | 2/14/2006 | | DONE |
|
|
|