To provide required monitoring of the new required outside control and relocation of the backflow preventer (replaced) tamper. The required sprinkler monitoring system was installed and finaled 1/20/2006. (FIR05-00677) The PDS Fire Inspector to field verify functionality of the tamper switches. If additional appliances are required, a resubmittal will be necessary. No written comments. Battery calculations appear to be sufficient. Provide revised building map, including any architectural changes to the PDS Fire Inspector at time of inspection.

The associated sprinkler permit (FIR06-00122) is to modify the existing system riser to accommodate a required outside control; an acceptable option taken by the owner for this new 7,800-ft/2, one story wood framed office building. The underground fire service supply lead-in was installed under FIR05-00460. Overhead was installed under FIR05-00570. All fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-01669. The sprinklers are used for area increase. INSURANCE NETWORK AMERICA OFFICE BUILDING -

The associated building permit (BLD05-01669) is to construct a new 7,800 square foot, one story wood framed office building and related site improvements. All construction per the approved plans and attached comment list. DRH04-00128/JCM Insurance Network America Office Building -
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/10/20063/13/20063/13/2006APASS
DetailsForrest France
Fire alarm permit finaled.
INSP-Alarm Testing3/9/20063/10/20063/10/2006PPASS
DetailsForrest France
Fire alarm work passed field inspection.
Telephone call  3/6/2006 DONE
I called Ben Davis, Dave Evans Const. reminding him the 2/16 agreement for the TOC on this permit was based on having the sprinkler and alarm work finaled within 7 days, or no later than 3/1. The sprinkler work was just finaled on 3/3 and we haven't heard form the FA contractor. He will followup and get the FA inspection scheduled today.
Case Summary  3/5/2006 DONE
Issue and Print Permit  2/24/2006 DONE
Plan assigned to (Mary)2/17/2006 2/21/2006 DONE
Alarm Plan Check  2/21/2006 PASS
Approved pending PDS Fire Inspector field verification. No comments written.
PLANS/APPL TAKEN TO FRONT DESK  2/21/2006 DONE
Permit Ready to Issue  2/21/2006 DONE
Inspection Record Card- Fire2/21/2006 2/21/2006 DONE
Case Summary  2/17/2006 DONE
Application received  2/17/2006