INSP-Final Inspection | 6/1/2006 | 6/1/2006 | 6/1/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/25/2006 | 5/25/2006 | 5/25/2006 | P | PASS |
Troy Cobbley
|
|
|
According to Adam the above ground hydro test passed. It was witnessed by the general contractor. Test papers will need to be provided.
|
INSP-Sprinkler Rough-in | 5/11/2006 | 5/11/2006 | 5/11/2006 | P | PASS |
Troy Cobbley
|
|
|
Piping ok to cover above the ceilings. This was the only piping inspected.
|
Telephone call | | | 4/19/2006 | | DONE |
|
|
|
lft vm with jeff packham ###-#### that permit - 2nd review no fee
|
Sprinkler Plan Check | 3/28/2006 | | 4/18/2006 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 4/18/2006 | | DONE |
|
|
|
Took modified approved shell permit plans and documents to permit desk for releasing. 2nd Review.
|
Plan resubmittals received | | | 3/27/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 3/21/2006 | | 3/21/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/21/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/21/2006 | | DONE |
|
|
|
left mess that permit is ready
|
Issue and Print Permit | | | 3/21/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 2/27/2006 | | 3/20/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/27/2006 | | 3/20/2006 | | PART |
Bill Alexander
|
|
|
Re-Submittals Of The Following Items Are Required:
1. Most remote (roof) area verified does not scale to minimum requirement of 1500-ft/2 (1475-ft/2). Provide clarification by dimensioning area of operation on the plan. When identifying and verifying the most demanding area, provide the actual area and not just the minimum allowed by the code with the calc cover sheets and plan calc sticker. (BMC 7-01-50-IFC 901.2 and IFC 105.4)
2. This is a "shell" permit. Address shell permit information and submit separately permitting for the T.I. permit.
3. All overhead piping in this facility except 1" is addressed as thinwall.
a. Provide fitting type connecting the thinwall lines and lines to mains throughout this design submitted, meeting requirements addressed in NFPA 12.1.2(21).
b. Any fitting incorporating that exceeds the standard fitting friction loss chart shall have calculations modified accordingly.
4. All equipment installing that requires listing shall be submitted for review (for installation requirement verification).
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2006 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/15/2006 | | DONE |
|
|
|
Approved Early Start Request for "installation of rough-in sprinkler mains, lines and riser. The riser will be connedcted to the UG only after the UG is flushed and tested under FIR05-00850". Documentation forwarded to Bill A.
|
Application received | | | 2/27/2006 | | |
|
|
|
|
Case Summary | | | 2/27/2006 | | |
|
|
|
|