Permit Information
Permit NumberFIR06-00143
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 350 N MILWAUKEE ST
Project NameBOISE TOWNE SQUARE EXPANSION
Customer Number 
ePlanReview 
Description
BOISE TOWNE SQUARE EXPANSION - To modify an existing valve room (systems) FDC to a permanent and accessible location in a parking lot island. Fire sprinkler work involves modification to the existing FDC piping, adding 6" galvanized pipe and grooved elbow outside the wall and underground to a transition/retained fitting, 6" MJ ell then approximately 240'-0" of 6" C-900 PVC sloped to an accessible drain pit, bedded with sufficient drain rock. The installation of an approved drain valve and "scored" ball drain on the bottom of 6" underground line, accessible through the pit. The transition from 6" C-900 to 6" Galvanized riser piping, exposed above the ground to installation of a 6" x 2½" x 2½" x 2½" 90° approved (3-way), at an elevation between 24" and 48" provided with an approved, permanent and identifiable sign addressing the use and mall building areas this connection supports. This work is preparation for the construction of 12,395-ft/2, one story shell addition, for three future retail tenant spaces, on the south side of the existing mall, east of the main mall entry. This permit does not include any other fire sprinkler (overhead or underground). The Mall building is fully fire sprinklered. The sprinklers are used for area increase. The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002 the IFC-2003, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD06-00007.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/5/20074/5/20074/5/2007PPASS
DetailsTroy Cobbley
permit finaled
INSP-Supply line flush3/23/20063/23/20063/23/2006PPASS
DetailsTroy Cobbley
permit finaled
Sprinkler Plan Check3/1/2006 3/23/2006 PASS
DetailsBill Alexander
Phase #2 Overhead review.
Plan assigned to (Bill)3/9/2006 3/23/2006 DONE
DetailsBill Alexander
Phase #2 Overhead Piping.
PLANS/APPL TAKEN TO FRONT DESK  3/23/2006 DONE
Inspection Record Card- Fire3/23/2006 3/23/2006 DONE
Permit Ready to Issue  3/23/2006  
Telephone call  3/23/2006  
called ###-#### and left voicemessage for Brad that permit is ready and fee
CHANGE STATUS TO (ISS)  3/23/2006 DONE
picked up plans
(F) Reprint permit  3/23/2006 DONE
INSP-Sprinkler Rough-in3/20/20063/21/20063/21/2006APASS
DetailsTroy Cobbley
The remaining section of the underground is ok to cover.
Miscellaneous action  3/21/2006 DONE
permit and plans were picked up
(F) Reprint permit  3/21/2006  
INSP-Sprinkler Rough-in/Hydro3/16/20063/16/20063/17/2006PPART
DetailsTroy Cobbley
Underground piping up to the 11 1/4 is ok to cover. Per contractor the piping is relocated 3' over to be under the new sidewalk and landscaping which will give it a 4'-6" bury.
Sprinkler Plan Check3/6/2006 3/9/2006 PASS
DetailsBill Alexander
Miscellaneous action  3/9/2006 DONE
Emailed revised review comments to Brad Bettencourt.
Plan assigned to (Bill)3/1/2006 3/6/2006 DONE
Telephone call  3/6/2006  
Informed Brad (Treasure Valley Fire Protection) ###-#### to pick up FAILED permit per Bill Alexander 3-6-06 eus
Issue and Print Permit  3/6/2006 DONE
Sprinkler Plan Check3/1/2006 3/6/2006 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  3/6/2006 DONE
Inspection Record Card- Fire3/6/2006 3/6/2006 DONE
Issue and Print Permit  3/6/2006 DONE
Plan resubmittals received  3/6/2006  
Miscellaneous action  3/3/2006 DONE
Returned to permit desk since scope of work exceeds allowable quick permit. Cannot read or follow riser modification work.
Application received  3/1/2006  
Case Summary  3/1/2006 DONE
Plan resubmittals received  3/1/2006 DONE
DetailsBill Alexander
Phase #2 Overhead review.