INSP-Final Inspection | 3/21/2007 | 3/22/2007 | 3/23/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 7/25/2006 | 7/26/2006 | 7/26/2006 | P | CANC |
Troy Cobbley
|
|
|
Wrong inspection type called in. Should be for a final.
|
INSP-Final Inspection | 7/26/2006 | 7/26/2006 | 7/26/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is approved with dave hanniman's permission until the south tenant space has been completed.
|
FIR-Aging Inspection | 6/30/2006 | 6/30/2006 | 7/5/2006 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
Sprinkler Plan Check | 4/10/2006 | | 5/1/2006 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 5/1/2006 | | DONE |
|
|
|
Took approved plans to permit desk for retunring. 2nd Review-No Fee.
|
Inspection Record Card- Fire | 5/1/2006 | | 5/1/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/1/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/1/2006 | | DONE |
|
|
|
called ###-#### and left message for Randy Bowron that permit is ready and fee
|
CHANGE STATUS TO (ISS) | | | 5/1/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/1/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/10/2006 | | |
|
|
|
|
Issue and Print Permit | | | 3/31/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 3/8/2006 | | 3/30/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/9/2006 | | 3/30/2006 | | PART |
Bill Alexander
|
|
|
Re-Submittals Of The Following Items Are Required:
1. FP1. Riser shall be provided with minimum dimensioning on it. Some critical required dimensioning is floor to center of the system riser piping, an acceptable FDC (w/elevations), critical listing installation requirements for the flow switch, etc. It would wise and helpful to include pipe sizing (not just as related in the riser keyed notes).
2. FP.1. Provide/Finish elevation dimensioning of the FP1 Section "A-A" and "B-B" on FP1.
3. Since the designer has submitted one package for 4 permits, provide a floor plan that addresses the (proposed) tenant T.I.'s in regard to locations and wall boundaries.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/30/2006 | | 3/30/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/30/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/30/2006 | | DONE |
|
|
|
called ###-#### and left message for Randy with Alicia that permit is ready and fees
|
Telephone call | | | 3/27/2006 | | DONE |
|
|
|
2:30 pm. Call De Best Fire Protection and talked to Matt regarding this project. Building permit attached is a a shell permit and plans submitted is complete shell and T.I. Address has no shell work associated. Address on the permit application does not match the building permit? He said he will check it out get back with me.
|
Application received | | | 3/8/2006 | | |
|
|
|
|