INSP-Final Inspection | 11/21/2007 | 11/27/2007 | 11/27/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 10/29/2007 | 10/30/2007 | 10/30/2007 | A | FAIL |
Troy Cobbley
|
|
|
The duct detector in the conference room did not shut down the hvac unit. All other items are ok. A map for the facp and nfpa 72 forms will be needed at the next inspection.
|
Issue permit | | | 9/27/2007 | | |
|
|
|
|
Plan assigned to (Mike) | 9/7/2007 | | 9/26/2007 | | PASS |
|
|
|
9/26/2007 09:38:08 MWT - activity updated through activity FIRA22 from case FIR06-00178.
|
Alarm Plan Check | | | 9/26/2007 | | PASS |
|
|
|
Fire Alarm Review 3rd Plan Modification
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2007 | | |
|
|
|
Ready for Issue
|
Inspection Record Card- Fire | 9/26/2007 | | 9/26/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/26/2007 | | DONE |
|
|
|
left vm for bob fetterly at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/26/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/7/2007 | | |
|
|
|
|
INSP-Final Inspection | 8/30/2007 | 9/5/2007 | 9/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
One of the new a/v's in the exam rooms did not function, the existing devices need to be mounted at the code compliant heights as per the city approved drawings and manometer test need to be performed on the duct smoke detectors as requested on the previous correction notice. The duct detector will need to be tested for functionality as well.
|
INSP-Final Inspection | 6/12/2007 | 6/14/2007 | 6/14/2007 | A | FAIL |
Troy Cobbley
|
|
|
there were no city review notes or approved data sheets. See the city approved plans for locations where a/v's need to be added in exam rooms and candellas changed to what is marked on the approved plans.. Also it appears that all of the new duct smoke detectors are improperly placed and the incorrect sample tubes utilized. A manometer test will be required. Only one detector was tested and that was just to make sure the detector shut the unit down imediately. The supervision of the NAC panels by the facp has been tested ok. All of the existing device locations are too low to meet code compliance which Bob was going to verify could remain. One existing device has not been changed out to a new device and is marked on the plans.
|
FIR-Aging Inspection | 8/11/2006 | 8/11/2006 | 8/11/2006 | | NR |
Troy Cobbley
|
|
|
Per Amy with CSHQA the work is still in progress and they are waiting for as-builts.
|
Issue and Print Permit | | | 5/3/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/1/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/1/2006 | | 5/1/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/1/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/1/2006 | | 5/1/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/1/2006 | | DONE |
|
|
|
Spoke with David and told him permit ready & fees @10:38am 5/1/06 BAS
|
Plan assigned to (Mary) | 3/15/2006 | | 4/29/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 4/29/2006 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/21/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 3/27/2006 | | FAIL |
|
|
|
Faxed comments to Stephanie Cobbley (CSHQA) 3/29.
|
Agreement of Future work | 3/20/2006 | | 3/20/2006 | | DONE |
|
|
|
Agreement to complete this permit for installation of an approved manual fire alarm system with approved a/v devices throughout the building by 12/31/2006 signed by D. Hanneman and G. Slane on 3/20/2006. This agreement will allow approval for occupancy of TI's within the building within the period of 3/20/06 to 12/31/06, prior to the completion of the required alarm devices within those spaces, as long as the terms of this agreement are being complied with.
|
Application received | | | 3/15/2006 | | |
|
|
|
|
Case Summary | | | 3/15/2006 | | DONE |
|
|
|
|