INSP-Final Inspection | 6/12/2006 | 6/12/2006 | 6/13/2006 | P | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
INSP-Alarm Testing | 6/12/2006 | 6/12/2006 | 6/12/2006 | P | PASS |
Forrest France
|
|
|
Required corrections have been made and verified for completion, fire alarm passed field inspection.
|
INSP-Alarm Testing | 6/8/2006 | 6/8/2006 | 6/8/2006 | P | FAIL |
Troy Cobbley
|
|
|
Duct smoke detectors are mounted on angles and near 90's. Provide differential pressure readings to verify they work. Provide some means of resetting the duct smoke detectors other than accessing above the ceiling such as a breaker, key or panel reset. The descriptors for the contact ID points at the monitoring station had not been set up yet. Need to retest devices to reverify points.
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2006 | 6/8/2006 | 6/8/2006 | P | CANC |
Forrest France
|
|
|
Phone #: ###-#### Internet Inspection Request from: David Uli Inspection cancelled from web by: David Uli
|
Issue and Print Permit | | | 3/30/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 3/15/2006 | | 3/29/2006 | | DONE |
|
|
|
|
Alarm Plan Check | 3/15/2006 | | 3/29/2006 | | PASS |
Troy Cobbley
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2006 | | DONE |
Troy Cobbley
|
|
|
|
Inspection Record Card- Fire | 3/29/2006 | | 3/29/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/29/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2006 | | DONE |
|
|
|
called ###-#### and left message for Rick Jackson with Cathy that permit is ready and fee
|
Plan resubmittals received | | | 3/28/2006 | | |
|
|
|
|
Case Summary | | | 3/28/2006 | | DONE |
|
|
|
|
Case Summary | | | 3/15/2006 | | |
|
|
|
|
Application received | | | 3/15/2006 | | |
|
|
|
|