INSP-Final Inspection | 4/7/2006 | 4/10/2006 | 4/10/2006 | A | PASS |
Forrest France
|
|
|
Corrections have been made, modifications tested, signals verified, fire alarm inspection passed.
|
INSP-Alarm Testing | 4/7/2006 | 4/7/2006 | 4/7/2006 | P | FAIL |
Troy Cobbley
|
|
|
four supervisory signal were sent but per the monitoring agency only three had been received. Need to test the elevator lobby smoke since it was relocated from the deck to the new ceiling.
|
Issue and Print Permit | | | 4/3/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/30/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/30/2006 | | DONE |
|
|
|
called ###-#### and left message w/receptionist for John that permit is ready
|
Alarm Plan Check | | | 3/29/2006 | | PASS |
|
|
|
Approved pending PDS Fire Inspector field verification. No comments written.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/29/2006 | | 3/29/2006 | | DONE |
|
|
|
|
Application received | | | 3/16/2006 | | |
|
|
|
|
Case Summary | | | 3/16/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 3/16/2006 | | | | |
|
|
|
|