INSP-Final Inspection | 10/5/2006 | 10/11/2006 | 10/11/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
Sprinkler Plan Check | 3/31/2006 | | 4/3/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/3/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 3/17/2006 | | 4/3/2006 | | DONE |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 3/31/2006 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 3/17/2006 | | 3/20/2006 | | FAIL |
Bill Alexander
|
|
|
Re-Submittals Of The Following Items Are Required:
1. Clarification of obstruction was missing which affect the head placement and location.
a. Area was determined to be obstructed with: "Beam and Girder Construction." Steel floor deck supported by steel beams spaced 3'-0" to 7'-6" on center supported/framed into girders.
Provide revised fire protection plan that meets spacing requirements for identified and related obstruction construction.
|
Application received | | | 3/17/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|