INSP-Final Inspection | 6/21/2006 | 6/22/2006 | 6/22/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2006 | 6/21/2006 | 6/21/2006 | A | PART |
Troy Cobbley
|
|
|
Above ground hydro test passed but the forward flush failed.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2006 | 6/20/2006 | 6/20/2006 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2006 | 6/12/2006 | 6/12/2006 | A | PASS |
Troy Cobbley
|
|
|
sprinkler heads added at the beam obstructions..
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2006 | 6/5/2006 | 6/5/2006 | P | FAIL |
Troy Cobbley
|
|
|
See city approved plans for locations where the upright sprinkler heads are being blocked by steel beams. Additional heads will be required. This inspection was for the overhead shell system piping only and did not include the riser or tenant improvement spaces.
|
Issue and Print Permit | | | 4/19/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 4/14/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 4/14/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/14/2006 | | |
|
|
|
called ###-#### and left message for Randy w/Alicia permit is ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/2006 | | DONE |
|
|
|
Per Bill A. do not issue until plan mod. approved for bld05-02752. Holbrook building shell, Light Syles of Boise TI, and Mortgage Company fire plans all attached. Bill called Debest to tell them permit not ready. Will watch for issuance of plan mod.
|
Plan assigned to (Bill) | 3/22/2006 | | 4/13/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/22/2006 | | 4/13/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 4/13/2006 | | |
|
|
|
FIR permit not directly related to parcel tag 4-13-06 eus
|
Inspection Record Card- Fire | 4/13/2006 | | 4/13/2006 | | DONE |
|
|
|
FIR permit not directly related to parcel tag 4-13-06 eus
|
Application received | | | 3/22/2006 | | |
|
|
|
|