INSP-Final Inspection | 6/23/2006 | 6/27/2006 | 6/27/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection.
|
INSP-Sprinkler Rough-in | 6/21/2006 | 6/22/2006 | 6/22/2006 | P | PART |
Forrest France
|
|
|
Sprinkler rough-in is acceptable for cover.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/27/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 3/30/2006 | | 4/25/2006 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Plan resubmittals received | | | 4/25/2006 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 4/25/2006 | | 4/25/2006 | | PASS |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 3/31/2006 | | 4/3/2006 | | FAIL |
Bill Alexander
|
|
|
Re-Submittals Of The Following Items Are Required:
1. This is a preaction system and requires certain installation requirements for the same which are different than wet systems.
a. Provide return bends as required per 7.4.1.1(3).
b. Verify auxiliary drain piping and possible requirement for 8.15.2.5.3.1 or 8.15.2.5.3.3.
|
Application received | | | 3/30/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|