INSP-Final Inspection | 6/2/2006 | 6/5/2006 | 6/5/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 5/31/2006 | 6/2/2006 | 6/2/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hannimans permission until the correct covers are installed on the a/v's in the outdoor area. Life safety is ok to final when fire alarm is finaled.
|
Alarm Plan Check | | | 6/2/2006 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/2/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/2/2006 | | 6/2/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/31/2006 | | |
|
|
|
|
Case Summary | | | 5/31/2006 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/26/2006 | 5/30/2006 | 5/30/2006 | A | FAIL |
Troy Cobbley
|
|
|
keith; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Items need to be addressed prior to inspection:
1) Resubmittal required
2) Pull station at SE exit at 51"
3) duct detectors are not installed per manufacturer's installation requirements. Inspector will accept differential reading (inspector verifies) or third party measurements.
4) Ceiling mounted H/S are overspaced (internal)
5) Exterior H/S have Gentex WP covers, cutsheet required at resubmittal to verify no visual loss.
Tested the following:
Water flow: address 11
Tampers (5): address 12
PIV (1): address 13
|
Case Summary | | | 5/30/2006 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/26/2006 | 5/26/2006 | 5/26/2006 | P | FAIL |
Forrest France
|
|
|
HVAC units were not in a condition to allow testing of the duct smoke detectors (T-stats not installed), FACP currently in alarm due to ansul system testing, fire sprinkler riser devices not tested as sprinkler contractor has correction items to address, discussed some previously noted issues with alarm contractor including a/v spacing, back boxes, manual pulls, and as-builts. Due to conditions of the project no final inspection could be performed, requested contractor to reschedule when ready for final, also noted that EOL's have changed from approved plans.
|
INSP-Final Inspection | 5/25/2006 | 5/25/2006 | 5/25/2006 | P | FAIL |
Troy Cobbley
|
|
|
No real inspection was performed due to items found just walking around. Manual pull stations and the wall mounted a/v on the kitchen wall(facing dining) are mounted too high. Not all heights have been verified. Also the ceiling mounted a/v's are mounted above 10' which means reduced spacing is used. If, since spacing has not been checked yet, the a/v's are overspaced and the contractor wants to just increase the cd rating, resubmittals will be required. Mary was at this inspection as well and knows what is going on.
|
Inspection Record Card- Fire | 5/12/2006 | | 5/12/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/12/2006 | | DONE |
|
|
|
Spoke with Keith and told him that permit is ready & fees///5/12/06 @8:15am BAS
|
Permit Ready to Issue | | | 5/12/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/12/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 4/3/2006 | | 5/11/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 5/11/2006 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/11/2006 | | DONE |
|
|
|
|
Miscellaneous action | | | 5/8/2006 | | DONE |
|
|
|
The 4th resub came in this morning. I had a lengthy discussion with Keith Olstrom and maintained our position that we will not authorize an early start on this project, particulary now, in light of the fact that it was observed last Friday that they have already installed the SLC wiring. He conceded they had done the work, but had done it before they knew we might consider an early start request. So he felt we should overlook they action of working without a permit. I didn't agree with that reasoning. I told him the early request was originally denied due to the extent and nature of the problems with the design and now the the request will be denied because he violated the law by installing without approved plans or permission.
|
Plan resubmittals received | | | 5/8/2006 | | |
|
|
|
Mary F
|
Miscellaneous action | | | 5/5/2006 | | DONE |
|
|
|
Troy Cobbley stopped by Fuddruckers on my request, (I am trying to get the review comments to the GC, per Samuel rogers request, and did not have the fax number or name). He found fire alarm wire pulled into back boxes at pull stations and the FSA at the front entrance. He posted a "Stop Work Order" and a double fee will be imposed, work without permit.
|
Alarm Plan Check | | | 5/5/2006 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Keith Olstrom and Jack with Hilbers (GC) to teh job site trailer at ###-####..
|
Plan resubmittals received | | | 5/3/2006 | | |
|
|
|
|
Alarm Plan Check | | | 4/27/2006 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Keith Olstrom.
|
Plan resubmittals received | | | 4/20/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 4/13/2006 | | FAIL |
|
|
|
Resubmittal required. No written comments. Meeting with keith Olstrom (Vanguard) to discuss deficiencies.
1) plans and riser do not match
2) no voltage drop calculations
3) NAC circuits not defined in the battery calculation, incorrect current used in the calculation.
4) No addressing shown on the plans
5) insufficient visual coverage
6) FA permit application not complete
7) Smoke detectors indicated in restrooms, kitchen corridor and a heat detetor in the kitchen....why?
8) Ansul monitoring not shown on the installation plan
9) Remote annunciator not included in the battery calculation
|
Case Summary | | | 4/13/2006 | | DONE |
|
|
|
|
Case Summary | | | 4/3/2006 | | DONE |
|
|
|
|
Application received | | | 4/3/2006 | | |
|
|
|
|