INSP-Final Inspection | 4/14/2006 | 4/17/2006 | 4/17/2006 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. I met with the superintendant and went over possible obstructions by fixtures and explained the "three times rule" to him on sprinkler spacing. He will get with Commercial fire with possible changes.
|
Issue permit | | | 4/13/2006 | | |
|
|
|
|
Sprinkler Plan Check | 4/11/2006 | | 4/12/2006 | | PASS |
|
|
|
Recieved full sized drawings.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2006 | | DONE |
|
|
|
No Comments.
|
Inspection Record Card- Fire | 4/12/2006 | | 4/12/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/12/2006 | | 4/12/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/12/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/12/2006 | | DONE |
|
|
|
called ###-#### and left message that permit is ready
|
Plan assigned to (Bill) | 4/5/2006 | | 4/10/2006 | | FAIL |
|
|
|
Faxed drawings are not legible. Requested full size prints for further review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2006 | | DONE |
|
|
|
|
Miscellaneous action | | | 4/6/2006 | | DONE |
|
|
|
Early start request approved, since Bill is out for a week and the permit approval/review around will be approximately 3 weeks. Work to be limited to installation of overhead piping and drops to coordinate with framing. No connection of the new piping to the existing system will be made until the permit has been issued.
|
Application received | | | 4/5/2006 | | |
|
|
|
|