INSP-Final Inspection | 11/21/2006 | 11/21/2006 | 11/21/2006 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2006 | 11/14/2006 | 11/14/2006 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed inspection.
|
INSP-Sprinkler Rough-in | 10/5/2006 | 10/6/2006 | 10/6/2006 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in passed.
|
INSP-Sprinkler Rough-in | 5/2/2006 | 5/2/2006 | 5/3/2006 | P | NR |
Forrest France
|
|
|
Hydrostatic test not ready for inspection per contractor, to be rescheduled.
|
INSP-Supply line flush | 4/27/2006 | 4/27/2006 | 4/27/2006 | P | PART |
Forrest France
|
|
|
The remainder of UG fire supply line is good for cover. Supply line flush also completed satisfactory at this time.
|
INSP-Sprinkler Rough-in | 4/26/2006 | 4/26/2006 | 4/26/2006 | P | PART |
Troy Cobbley
|
|
|
Underground piping from the street to with in approximately 10'-0" of the building is ok to cover. The remaining section will be call in for a later inspection when installed. Per the sprinkler contractor the fire sprinkler monitoring system does not appear to be monitored by an outside agency. I notified ray criner via phone call and email. He stated he would follow up.
|
Plan assigned to (Bill) | 4/7/2006 | | 4/17/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/13/2006 | | 4/17/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/17/2006 | | 4/17/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/17/2006 | | DONE |
|
|
|
called ###-#### and told Jeff Anderson (Brad no longer there) that permit is ready and fee
|
Permit Ready to Issue | | | 4/17/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/17/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/13/2006 | | DONE |
|
|
|
|
Application received | | | 4/7/2006 | | DONE |
|
|
|
|