Permit NumberFIR06-00262
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 412 S 13TH ST
Project NameSPR UG PLAZA MIXED USED
Customer Number 
ePlanReview 
Description
PLAZA MIXED USED - To install approximately 115 feet of 6" C-900 PVC connected to an existing 8" water service supply main in 13th St., running east on the North side of West Grand Ave to a location near the Southeast corner and into the proposed 42 unit, 61,812-ft/2 5 story wood framed apartment building. This underground supply will provide a full NFPA 13 fire sprinkler system per Boise City Ordinance. This permitted work is associated with Section 2 of 2 portion of the building which contains 17 units, and is 25,764-ft/2. A two hour fire wall (also used as a horizontal exit) will be constructed to divide this facility into two separate buildings being constructed above a Type I-A parking garage, per City Ordinance 4-16. This permit is attached to BLD05-02750. The section 1 of 2 is associated with BLD05-02204 for the other side of the fire wall. Refer to BLD05-00926 for the parking garage. The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002 the IFC-2003, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/14/20076/15/20076/15/2007APASS
DetailsForrest France
Fire supply line permit finaled.
INSP-Sprinkler Rough-in11/2/200611/3/200611/3/2006ADEFR
DetailsForrest France
Wrong permit number called in, was intended for the overhead permit work.
INSP-Sprinkler Rough-in/Hydro10/16/200610/16/200610/16/2006PPART
DetailsForrest France
UG fire supply line is okay for cover, UG also passed hydrostatic test, noted marked locations for the FDC and WPI appear too low above finish grade.
INSP-Sprinkler Rough-in10/16/200610/16/200610/16/2006PCANC
DetailsForrest France
bruce - note: call 1/.2 hr prior to going out 5th floor; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
Issue and Print Permit  5/19/2006 DONE
Permit Ready to Issue  5/18/2006 DONE
Inspection Record Card- Fire5/18/2006 5/18/2006 DONE
Plan assigned to (Bill)4/11/2006 5/18/2006 DONE
Sprinkler Plan Check5/12/2006 5/18/2006 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  5/18/2006 DONE
Plan resubmittals received  5/12/2006 DONE
DetailsBill Alexander
Sprinkler Plan Check4/13/2006 4/17/2006 FAIL
DetailsBill Alexander
Re-Submittals Of The Following Items Are Required:
1. Plan is incomplete and/or unreadable. Information is lacking and clarified, (correct) dimensioned plan/s is required. Information shall be all encompassing with enough detail to clarify the full scope of the work involved with the permit requested. "U.G. Permit" needs clarified in order to address minimum installation code.
a. Provide clarification of all piping installing, how all is entering/leaving the facility which shall include but may not be limited too:
1. Elevations,
2. Thrust protection,
3. Clearance,
4. Type and size of all pipe installing,
5. Identify all fittings, valves, transition, etc.
6. Clarified location of P.I.V.
7. Elevation of P.I.V addressing limit required per NFPA 13.
8. Provide elevation of F.D.C. addressing limits allowed per the IFC and NFPA 13 and 14.

2. Provide clarification of symbols, (differentiate between a hydrant and fire department connections).

3. Provide data submittals on the FDC. Address whether the FDC is a combination FDC/Standpipe, and include the correct identification of the same incorporating on the plan.

4. Provide clarification that hydrant/s are not connected to the fire sprinkler service supply line installing, meeting requirements of the BMC-IFC.

5. Include depth of bury of all pipe installing, measured from the top to finish grade.

6. This facility will most likely require a standpipe required during construction. Will the FDC installing be connected to the standpipe required under IFC 1413? If so, address this on the plans.
NOTE: Temporary standpipes in buildings being constructed will require prior permit approval before installation or any work for the same.
Telephone call  4/17/2006 DONE
tlk to john warnick ###-#### that permit failed and needs to be picked up
Case Summary  4/11/2006 DONE
Application received  4/11/2006  
Inspection Record Card- Fire5/18/2006