INSP-Final Inspection | 5/5/2006 | 5/5/2006 | 5/5/2006 | P | PASS |
Troy Cobbley
|
|
|
Fire alarm finaled
|
Permit Ready to Issue | | | 5/5/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/5/2006 | | 5/5/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/5/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 4/17/2006 | | 5/4/2006 | | DONE |
|
|
|
|
Alarm Plan Check | | | 5/4/2006 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2006 | | DONE |
|
|
|
|
Miscellaneous action | | | 5/3/2006 | | DONE |
|
|
|
Troy Cobbley stopped at the site and found the FACP has been installed without a permit. The electrician stated that Patrick Gill (Idaho Alarms) installed it.
|
Plan resubmittals received | | | 5/3/2006 | | |
|
|
|
|
Alarm Plan Check | | | 4/20/2006 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Patrick Gill.
|
Application received | | | 4/17/2006 | | |
|
|
|
|
Case Summary | | | 4/17/2006 | | |
|
|
|
|