Permit Information
Permit NumberFIR06-00288
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 950 W BANNOCK ST Unit: 520
Project Name10TH & BANNOCK-5TH FLR
Customer Number 
ePlanReview 
Description
MOORE, SMITH, BUXTON & TURCKE - BANNER BANK BLDG - STE 520 * This building is fire sprinklered because it is a high-rise. To add 12 SSP and relocate 12 existing SSP's for the construction of a new 4,279-ft/2 office tenant space located on the 5th story of a 182,950-ft/2, twelve story concrete and steel framed office and retail, w/parking, high rise shell and core building. Fire sprinkler work is related to the installation of Nordwall demountable nonbearing partitions. The access floor system and the suspended ceilings were installed under permit BLD05-02939. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The shell fire sprinkler permit was installed under FIR05-00594. This permit is attached to building permit BLD06-00324.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/31/20066/1/20066/1/2006APASS
DetailsForrest France
Final fire sprinkler inspection passed, permit finaled.
INSP-Final Inspection5/30/20065/31/20065/31/2006AFAIL
DetailsTroy Cobbley
sprinkler pendant is still overspaced in an east facing office.
INSP-Final Inspection5/26/20065/30/20065/30/2006AFAIL
DetailsTroy Cobbley
Pendant sprinklers overspaced. Small room rule can not be used. (This activity was added in error so we have changed the case status back to Issued.)
CHANGE STATUS TO (ISS)  5/30/2006 DONE
INSP-Sprinkler Rough-in5/19/20065/22/20065/22/2006APART
DetailsForrest France
Overhead rough-in is acceptable for cover, escutcheons at some locations need adjustment.
CHANGE STATUS TO (ISS)  5/9/2006  
plans picked up
(F) Reprint permit  5/9/2006 DONE
INSP-Final Inspection5/4/20065/5/20065/5/2006ACANC
DetailsForrest France
ROD; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Sprinkler Plan Check4/27/2006 5/5/2006 PASS
Review comments attached to plans.
PLANS/APPL TAKEN TO FRONT DESK  5/5/2006 DONE
Permit Ready to Issue  5/5/2006 DONE
Inspection Record Card- Fire5/5/2006 5/5/2006 DONE
Telephone call  5/5/2006 DONE
Called and left message for Gerald that permit is ready & fees///5/5/06 @4:21pm BAS
INSP-Final Inspection4/26/20064/27/20064/27/2006ANR
DetailsForrest France
Wrong project permit number called in for inspection by contractor.
Plan resubmittals received  4/26/2006  
Plan assigned to (Bill)4/18/2006 4/24/2006 DONE
Sprinkler Plan Check4/18/2006 4/24/2006 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  4/24/2006 DONE
Case Summary  4/24/2006 DONE
Inspection Record Card- Fire4/24/2006 4/24/2006 DONE
Permit Ready to Issue  4/24/2006 DONE
Telephone call  4/24/2006  
tlk to gerald ebeling ###-#### that permit and fees are ready to be picked up
Issue and Print Permit  4/24/2006 DONE
Application received  4/18/2006