INSP-Final Inspection | 5/31/2006 | 6/1/2006 | 6/1/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2006 | 5/10/2006 | 5/10/2006 | A | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover at the drop ceiling areas, dry pendent not installed in the cooler at this time as the cooler is not constructed.
|
Issue permit | | | 5/8/2006 | | DONE |
|
|
|
|
Application received | | | 5/2/2006 | | |
|
|
|
|
Sprinkler Plan Check | 5/2/2006 | | 5/2/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/2/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/2/2006 | | 5/2/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/2/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/2/2006 | | DONE |
|
|
|
lft vm with tom dutkus ###-#### that permit and fees are ready to be picked up
|
Plan assigned to (Bill) | 5/2/2006 | | | | |
|
|
|
|